Napier Courier

Damaged pipe causing concern

-

Months after a Napier wastewater pipe was damaged, contractor­s working to repair the problem are back at square one.

The pipe, belonging to Pan Pac Forest Products, was first flagged by a resident in September, who reported discoloura­tion near the water’s edge at Whirinaki Beach.

It was found to be seepage of treated wastewater from Pan Pac’s wastewater treatment plant.

At that time, the Pan Pac Forest Products managing director Doug Ducker advised residents in a letter that a section of pipeline “has sustained some form of damage or deteriorat­ion with small amounts of wastewater escaping”.

It was occurring about 70 metres from Whirinaki Beach Rd rather than the usual 2.4 kilometres.

Towards the end of December, work on the pipe was expected to be completed “within the next few days”, meaning early this month.

However, Hawke’s Bay Regional Council group manager regulation Liz Lambert said she was advised on Thursday by Pan Pac that its first solution had failed, and it was now trying a different option.

She said the location of the pipe, both being in a “very active coastal area” as well as being buried undergroun­d had contribute­d to the delays.

“They have been working right from the time it started, but sometimes just the physical location of some of these pieces of infrastruc­ture means that it is more difficult and it does take more time because you need more specialist equipment and materials.”

They initially went about sealing the breakage from the inside, by “pouring concrete”, but weather and sea conditions prevented the work for some time. Despite eventually being able to get in, it ultimately did not work.

“Their approach now is they are going to look to insert a sleeve inside the pipe to seal it from inside,” Lambert said.

Lambert said they have been kept “fully informed” through out the process.

“Right from when the leakage was detected by Pan Pac, they let us know and one of our compliance officers has been liaising with them the whole time.”

The mill began operating in 1973, at which time it had a short outfall pipe into the ocean and in 2017 the discharge pipeline was extended from 300m to 2.4km.

Lambert said they estimated it was between 2 and 5 per cent of the actual discharge that was leaking out. “It is not a significan­t environmen­tal risk but it doesn’t look good because of the discoloura­tion which is caused by the product in the discharge. They have fenced off either side of the pipe and put up warning signs.”

The cost of the repairs were being met by Pan Pac.

 ?? PHOTO /WARREN BUCKLAND ?? The discoloure­d sea as constructi­on work on Pan Pac Forest Products Limited outflow pipe on Whirinaki Rd continues.
PHOTO /WARREN BUCKLAND The discoloure­d sea as constructi­on work on Pan Pac Forest Products Limited outflow pipe on Whirinaki Rd continues.

Newspapers in English

Newspapers from New Zealand