North Taranaki Midweek

Plans changed for Yarrow Stadium roof

- GLENN MCLEAN

The plans for Yarrow Stadium’s contentiou­s $70 million rebuild have changed again with the West Stand’s roof now being replaced by a fabric version of PVC.

Questions were raised about the installati­on of the roof after contractor­s failed to deliver on an earlier deadline to have it in place before the start of the national provincial rugby championsh­ip.

That left Taranaki Rugby, as a tenant of the stadium, to apologise to season ticket holders, who, along with the public, had to watch from the sidelines in an uncovered stand.

At the time of the announceme­nt, the Taranaki Regional Council blamed bad weather for not giving contractor­s enough dry days to paint the stand’s supports for the old roof to be erected.

However, late last month, the council issued a release saying work had started on installing a new fabric roof, which was expected to be completed by Christmas.

Taranaki Regional Council chairperso­n Charlotte Littlewood hailed the work as ‘‘another milestone’’ on the ‘‘road to delivering the best regional stadium in the country.’’

When questioned about why 2250 square metres of high-spec PVC was being used on the West Stand, council director of corporate services Mike Nield said an engineerin­g report on the previous West Stand roof found repairing it, as planned, had potential costs and risks.

‘‘Once that decision was made, we had planned to use PVC as the roof on the new East Stand will be PVC and there was the opportunit­y to use the same high-spec, long-lasting material and have a consistent look to the roofs on both stands,’’ he said.

While he did not answer questions about the cost of the new roof, Nield said it was expected to have a lifespan of around 50 years.

In July, former Taranaki Regional Council chairman David MacLeod said the stand’s rebuild would be delivered on budget despite the challengin­g constructi­on conditions.

It followed a budget blowout on the project, which jumped from $50m to $70m and included the Government pitching in another $10m, along with an interest-free loan of up to $5m. It had already committed $20m.

The new East Stand is due to be built by 2024, although in last week’s statement, Littlewood said that could now be early 2025. That is despite the seating capacity being reduced from 4000 to 1800.

The redevelopm­ent project was announced in 2019, after the two grandstand­s were declared earthquake-prone in 2017 and 2018.

 ?? VANESSA LAURIE/STUFF ?? Work has started on installing a new PVC roof on the West Stand at Yarrow Stadium.
VANESSA LAURIE/STUFF Work has started on installing a new PVC roof on the West Stand at Yarrow Stadium.

Newspapers in English

Newspapers from New Zealand