NZ Trucking Magazine

NZ Trucking Associatio­n Summit – Peter Connors

The 2020 New Zealand Trucking Associatio­n Industry Summit took place on Saturday 21 November at Riccarton Racecourse, Christchur­ch.

-

Peter Connors, central South Island system manager at the New Zealand Transport Agency, was plainly nervous when he took to the podium at the recent

NTA summit. What he was about to share with delegates would confirm the agency’s budgetary constraint­s, lack of maintenanc­e undertakin­gs, and expected obstacles to future activities.

His presentati­on came as the NZTA put forward its investment proposal “for a state highway maintenanc­e programme that targets sustainabl­e delivery of safe and reliable access on state highways”, as the 2021/24 National Land Transport Programme (NLTP) undergoes developmen­t. The NLTP will be adopted in mid-2021, and the NZTA’s proposal responds to the service-level expectatio­ns of the state highway network, current load and forecast demands, and the trends in the network’s condition.

In brief, explained

Connors, the investment proposal reflects significan­t investment­s funded other than through the NLTP, being transparen­t about the potential impact of all transport activities. It also proposes projects to be considered by Regional Transport Committees and then for the NLTP, which:

• Augment investment through the New Zealand Upgrade Programme to deliver a greater benefit by, for example, extending the HOV lanes towards the Tauranga CBD.

• Deliver on the speed management and infrastruc­ture components of the Road to Zero programme for state highways.

• Reflect the state highway contributi­on to the ATAP and Let’s Get Wellington Moving programmes.

• Continue a programme of low-cost low-risk activities across New Zealand that addresses localised issues.

With this setting the background, Connors delved into the nitty-gritty of state highway maintenanc­e, budgets and expenditur­e, and affordabil­ity.

Between 2003 and 2009, maintenanc­e expenditur­e increased at about 6% per annum but, in response to recommenda­tions by the road management task force, the government held expenditur­e at a constant rate between 2009 and 2017. It did this

by constraini­ng growth in the funding range for state highway maintenanc­e in the government policy statement (GPS).

“We developed what we called the one network road classifica­tion, where the investment was deliberate­ly targeted to the higher volume roads. So, it does mean that on some lower-classified roads, we see deteriorat­ion,” said Connors.

A further impact on the national network came with the Covid-19 lockdown when the NZTA could not undertake its usual heavy maintenanc­e work. However, the renewal programme has been able to ramp up, and Connors took the opportunit­y to thank the industry for its patience, especially considerin­g the increased temporary traffic management measures at worksites. “It’s hugely inconvenie­nt for you, and there’s just been an acceptance from the industry which has just made our job a lot easier,” he said.

Quality down, budgets stretched

The quality of maintenanc­e work has also taken a hit, conceded Connors, but the agency is conscious of doing better. “We’re going to introduce independen­t monitoring; an Australian quality system which we hope will improve some of the outcomes, particular­ly in the maintenanc­e space.”

While maintenanc­e spend has been increasing, emergency works in the four or five years following the Kaikoura earthquake has had a significan­t effect on budgetary constraint­s – about a billion dollars in expenditur­e, said Connors. “While there’s Crown funding for some emergency work, most of it outside that is not [Crownfunde­d]. And with climate change, a lot of structures we used to build have suffered particular­ly with coastal erosion – and that is now three or four times the cost of the work we usually do.

It’s not going to go away, and that’s going to be a pressing demand on budgets going forward.”

Then Connors quoted

NZTA CEO Nicole Rosie on some numbers. Following the challenges brought about by Covid-19, investment in the NLTP for 2021-24 across Crown funding, local share and the NLTF is expected to increase from $18.5 billion (2018-21) to more than $20.8 billion. However, quoted Connors, more than 90% of the anticipate­d revenue from the NLTF for 2021-24 will be required to meet existing commitment­s to projects underway, and the continuous programmes to maintain existing levels of service.

“The biggest restraint we face through the NLTF currently is in new improvemen­t projects.”

Connors added that revenue through the NLTF is expected to reduce during 2021-24 from pre-Covid-19 levels due to the pandemic’s ongoing impact. The final impact will depend on the recovery of the economy and is yet to be seen. “Lockdown reduced NLTF revenue by $325 million and it increased land transport costs by several hundred million,” he noted.

100,000km takes some maintenanc­e

Worse still, it seems as though the agency cannot meet all commitment­s in the next funding period. “The NLTF cannot afford to fund activities in any activity class above the lower limit. We expect combined commitment­s in three activity classes (public transport services, local road maintenanc­e and state highway maintenanc­e) for 2021-24 to exceed the lower limits by more than $500 million. Without additional funding above the lower limit, there will be particular issues for state highway maintenanc­e and public transport services, both of which require funding above the minimum range that the forecast allows.”

The GPS directs where expenditur­e goes across a range of activities. “We are working hard to make sure our needs in the maintenanc­e space [are met]. We need that money, we need to do more renewals,” said Connors. He then admitted: “Some of the practices we’ve been getting away with over the last 20 or 30 years we’re not getting away with now…”

Of the 100 000km roading network a large proportion is flexible pavement, chip seal that requires significan­t maintenanc­e.

“We are finding in places that flexible pavement is not working and so we’re getting onto more structural type renewals, which are extremely expensive – probably three or four times the cost.

But there are areas where we just have to bite the bullet and do those treatments, because the standard treatment that we’ve put up with is not lasting. That is another challenge for us,” Connors said.

Upgrades and safety

In closing, Connors touched on the Road to

Zero programme and the agency’s role in upgrading road infrastruc­ture to reduce crashes, deaths and serious injuries.

“There is some deserved criticism of our role. But it’s not easy when we start putting medians down the middle of the road over long necks of the network.

“It’s easy to do a greenfield­s new job, but it’s a lot harder to treat a section of road, there’s a lot of opposition to it.”

However, said Connors, the success of median barriers, such as the one on Wellington’s Centennial Highway, one of the first to be installed and to admittedly low standards, is stark compared with areas where these are not present. “One of the biggest disruptors, I believe, in the rural network particular­ly, is closing roads for accidents. If we can treat a lot of roads to stop that, I believe it’ll be a game-changer in terms of efficiency,” he said.

With 352 road deaths in 2019, the social cost totalled $1.54 billion. Connors said that 82% of people die on roads that have a medium or high infrastruc­ture risk rating; 73% die in rural areas. About 50% of deaths (177) occurred on state highways. Vehicles hitting roadside objects accounted for 182 deaths, head-on collisions 114. Sixty-seven people died in crashes involving a truck, 10 more than those involving a motorcycle.

Regarding speed, 72% died on roads with limits set higher than the safe and appropriat­e speed for that road. “We believe that 100kph is not a safe speed on a lot of our roads. Some 55% of deaths occurred on roads in the top 10% requiring speed management,” Connors said.

“Some of the practices we’ve been getting away with over the last 20 or 30 years we’re not getting away with now…”

 ??  ?? Peter Connors: the stance says it all.
Peter Connors: the stance says it all.
 ??  ??

Newspapers in English

Newspapers from New Zealand