Otago Daily Times

May date given for opening of twolane bridge

- TRACEY ROXBURGH

THE countdown is on for the longawaite­d opening of Queenstown’s new twolane bridge between Kelvin Heights and Frankton.

Work first began on the $22 million bridge in January 2016. NZ Transport Agency senior project manager Phil Dowsett said both lanes were expected to open next month.

The NZTA did not give any indication of when in May the bridge may be fully operationa­l.

Mr Dowsett said work in recent weeks had focused on the creation of a new walking and cycling underpass and laying new water pipes in the bridge approaches to cater for the ‘‘large growth in develop ments’’ south of Queenstown.

That had been funded by the Queenstown Lakes District Council and it was easier to complete while the bridge was under constructi­on.

Further, utilities companies had commission­ed additional ducting to be installed beneath the bridge, ensuring it could continue to meet the increasing demands of the growing population, Mr Dowsett said.

‘‘Completing the work while the bridge is still under constructi­on is the best option and reduces inconvenie­nce to locals by removing the need to dig up the road again or limit access to the bridge in the future.

‘‘The ducting installati­on will take a couple of weeks and the contractor has pro grammed the work so it won’t have a significan­t impact on getting both traffic lanes of the new bridge open in May.’’

Piling for a new boardwalk at the southern end of the bridge and highway realignmen­t work was due to be completed this month, with rocks handpacked into nearly 800 steel baskets to create the wall behind it.

 ?? PHOTO: NZ TRANSPORT AGENCY ?? Easy access . . . Contractor­s work on the cycle and pedestrian underpass at the northern end of the new Kawarau Falls Bridge.
PHOTO: NZ TRANSPORT AGENCY Easy access . . . Contractor­s work on the cycle and pedestrian underpass at the northern end of the new Kawarau Falls Bridge.

Newspapers in English

Newspapers from New Zealand