AN Alexandra group who had ‘‘tried hard’’ to reinstate a walking and cycling bridge over Alexandra’s old bridge piers is ‘‘gutted’’ to find out the project is not feasible.

Strengthen­ing the piers and building a new bridge could have cost up to $3.3 million, and the walkway for the bridge would have had to be ‘‘very high’’ to be sufficient­ly above the 100year flood level, Vincent and Teviot Valley property and facilities officer Christina Martin told Vincent Community Board members at their meeting on Wednesday.

‘‘It would have to go near the top of the arch [of the piers], much higher than where the bottom of the bridge used to be, and there would need to be a gradient at either end for people to access the bridge. Aesthetica­lly, it wouldn’t look right.’’

Ms Martin said it had been a ‘‘hard call’’, but members of the Alexandra Suspension Bridge Working Group, formed in 2005, had realised the findings of a report from Beca engineers and consultant­s meant a bridge could not be reinstated, as they had initially hoped. This was ‘‘gutting’’ for them, and she praised the work they had done exploring the bridge options.

Working group member Clair Higginson said group members had ‘‘tried hard’’ to make the project work, ‘‘but in the end we realised it just couldn’t happen’’.

The Beca report said the ‘‘top end’’ estimate of strengthen­ing the bridge piers and constructi­ng a bridge would be $3.3 million, but using the piers as a gateway rather than part of the bridge structure would have needed a ‘‘lighter touch’’ in strengthen­ing.

However, two other options will now be investigat­ed.

One is a ‘‘clipon’’ to the blue road bridge, and the other is a new, standalone suspension bridge for cyclists and walkers.

The Central Otago Queenstown Trail Trust has been pledged $1.7 million of funding to build a bridge across the Clutha River in Alexandra as part of the $26.3 million project to build new cycle trails in Central Otago.

Board members adopted Ms Martin’s recommenda­tions, which were for the board to collaborat­e with the trail trust to ensure any clipon to Alexandra’s road bridge would be ‘‘sympatheti­c with the historic bridge piers’’.

A maintenanc­e strategy would be developed for the piers; the board would collaborat­e with the Alexandra Miners’ Village and Riverside Park Trust and the trail trust about the ‘‘whole river precinct landscape’’ from the Shaky Bridge to the boat ramp; and a viewing platform will be investigat­ed.

 ?? PHOTO: CENTRAL STORIES MUSEUM
AND ART GALLERY ?? Historic monuments . . . Alexandra’s new ‘‘blue’’ bridge is opened on July 5, 1958, alongside the original bridge, which opened in 1882.
PHOTO: CENTRAL STORIES MUSEUM AND ART GALLERY Historic monuments . . . Alexandra’s new ‘‘blue’’ bridge is opened on July 5, 1958, alongside the original bridge, which opened in 1882.

Newspapers in English

Newspapers from New Zealand