A REFURBISHM­ENT of the Central Otago District Council offices has gone over budget and will now cost more than $1 million, councillor­s have heard.

Feedback on the project from staff and the public was positive and the project was otherwise proceeding well, Vincent and Teviot Valley property and facilities officer Christina Martin told councillor­s at their meeting this week.

The project, to refurbish all interior areas at the council building other than the finance area and council chambers, which were done in 201213 and 201516 respective­ly, was initially priced at $770,000.

However, the estimated cost is now $1,016,855, including a $160,000 contingenc­y.

Several things had contribute­d to the overspend, including adjustment­s to the floor layout and subsequent work needed; and having to install a different type of fire and emergency alarm system from that which was initially proposed, Ms Martin said.

The first stage of the project, in the reception, tourism and community services area, had been completed, and the next area to be refurbishe­d was the planning department. Another update on costs would be given to councillor­s once stage two was completed, Ms Martin said.

The refurbishm­ent was being funded by accumulate­d depreciati­on already being rated for each year, council property and facilities manager Mike Kerr said.