Hospital site could be cleared by June
Mr Rae concluded it was, and losing Cumberland St heritage facades was unavoidable.
He said the hospital would bring significant benefits to the community.
However, some parts of the hospital project have not been sailing along quite so smoothly.
It is set to exceed its $1.4 billion budget and the Cabinet is yet to approve a detailed business case. The Cabinet has signed off on the case in principle.
New Dunedin Hospital project chairman Pete Hodgson said a quantitative risk analysis could not be completed in time for consideration by the Cabinet in September and a complete concept design was now almost ready to be signed off.
‘‘Those gaps are being rapidly filled,’’ he said.
Mr Hodgson said he was delighted the demolition consent had been granted.
Mr Barns said he was well aware of concerns about heritage at the site being lost.
‘‘We’re taking every step we reasonably can to mitigate these,’’ he said.
That included keeping a photographic and video record of the factory buildings.
Heritage New Zealand OtagoSouthland manager Jane Macknight said the buildings were a tangible link to the site’s history of land use, including as a brewery, distillery and confectioner.
Heritage New Zealand required the retention of the Dairy and Machine House building at the site to mitigate against the loss of heritage, she said.
In the end, no parties were actively opposed to the ministry’s application for demolition and they agreed on a set of conditions.
The ministry will have to submit a demolition management plan and a plan for removing asbestos.
It will have to make sure there are no adverse effects on the structural integrity or heritage values of surrounding heritage buildings — particularly the machine house building and the Allied Press building.
Allied Press — publisher of the Otago Daily Times — withdrew its opposition to the application before the November 2 hearing.
The ministry will need to take steps to minimise noise and vibration during demolition, as well as manage traffic and control dust.
Allied Press had earlier raised concerns about the potential for dust and vibration to affect the printing press.
The demolition consent period is for five years.
Some materials may be salvaged to retain items of heritage.