Otago Daily Times

End in sight for troubled motorway

- GEORGINA CAMPBELL

WELLINGTON: Constructi­on of Wellington’s troubled Transmissi­on Gully motorway is now more than 85% complete and the NZ Transport Agency is confident it will open next September.

The 27km road has suffered delays, cost blowouts, and is now the subject of a Government­ordered review.

It was meant to be open by April this year; then it was pushed back to before Christmas this year; and now it is due to open in September 2021.

The project is being built through a publicpriv­ate partnershi­p, the Wellington Gateway Partnershi­p (WGP), with CPB Contractor­s and HEB Constructi­on subcontrac­ted to carry out the design and constructi­on.

The total cost of the road has climbed to $1.25 billion after NZTA bailed out contractor­s twice due to issues including the Kaikoura earthquake, extreme weather events and the Covid19 pandemic.

But Wellington Gateway Partnershi­p chief executive

Sergio Mejia said yesterday he could see the light at the end of the tunnel and was confident the road would open next

September.

‘‘I’m certain we’re going to hit the target.

‘‘We’re fully committed and we’re on schedule.’’

Mr Mejia said he was proud of the team working on the fourlane motorway that will run from Mackays Crossing to Linden.

There are 570 people working on site.

When Transmissi­on Gully opens, about 25,000 vehicles are expected to use it each day. — The New Zealand Herald

 ?? PHOTO: ?? Major project . . . The Transmissi­on Gully constructi­on site at the Cannons Creek bridge, north of Wellington. The 230mlong bridge is four lanes and stands 60m above the stream below. THE NEW ZEALAND HERALD
PHOTO: Major project . . . The Transmissi­on Gully constructi­on site at the Cannons Creek bridge, north of Wellington. The 230mlong bridge is four lanes and stands 60m above the stream below. THE NEW ZEALAND HERALD

Newspapers in English

Newspapers from New Zealand