Rotorua Daily Post

Rotorua Museum reopening delayed by three years

-

hopefully, there won’t be any more.”

Asked about the new issues, Rotorua Lakes Council operationa­l group manager Jocelyn Mikaere said as the design reached “the most complex atrium area, the challenge of strengthen­ing a heritage building sited on geothermal ground resulted in buildabili­ty and risk questions”.

“It is prudent to assess alternativ­es now versus continuing without adequate risk mitigation­s in place.”

Additional expertise has been brought in to help resolve issues that surfaced during the pre-constructi­on phase and needed further investigat­ion and advice about structural solutions for the building.

“It’s important that we have the best informatio­n to get the right solution for the complexiti­es we are dealing with, such as 1908 unreinforc­ed pumice masonry structures, a very heavy roof and challengin­g geothermal ground conditions,” Mikaere said.

Mikaere said key stakeholde­rs, including funders, had been kept informed.

A detailed seismic assessment of the museum building the year after the earthquake showed it met just 15 per cent of New Zealand’s earthquake safety standards. Buildings at 33 per cent or below are considered earthquake-prone.

The location

on

geothermal ground also contribute­d to the rebuild being considered as one of the most challengin­g and complex strengthen­ing projects happening in New Zealand, the council’s release said.

In response to a Rotorua Daily Post reader who asked on Facebook what the director of the museum — Lizzie Marvelly, appointed last year — would be doing until the museum reopened, the Rotorua Museum page replied that she and her team will be working on extensive community engagement, conservati­on and design programmes.

All museum exhibition­s would need to be redesigned and reinstalle­d and other offerings — education and public programmes, outside the walls daily tours, retail, hospitalit­y — needed redevelopm­ent.

Manatu¯ Taonga Ministry for Culture and Heritage deputy chief executive delivery Tamsin Evans said the ministry had been kept informed of the challenges with the

exhibition building but was not involved in the delay decision.

Mayor Steve Chadwick said: “Our iconic museum is much loved by both our local community and visitors and we all want to see it reopened as quickly as possible, but will have to remain patient as these complexiti­es are worked through.

“We’ve always said it was a complex building and that it wasn’t going to be a simple project. We knew we would need to take the time and care necessary to restore it.”

Once the geothermal and structural investigat­ions are done, the council expected to host several update events to inform the community on the progress of the project.

 ?? ?? Monty Morrison
Monty Morrison

Newspapers in English

Newspapers from New Zealand