Sunday Star-Times

Cyclone Gabrielle: A year on, are we more resilient?

Power firms and telcos front up on what they have done to ‘build back better’ and what’s still to do. Tom Pullar-Strecker reports.

-

If a storm identical to Cyclone Gabrielle were to strike the country on the first anniversar­y of that disaster on Wednesday, it might cause a little less disruption.

About 240,000 homes, or 11% of households, lost power during the peak of Cyclone Gabrielle on Valentine’s Day last year, according to Electricit­y Networks Aotearoa.

Electricit­y companies and telcos are reporting worthy progress improving the resilience of their networks since then, with more improvemen­ts in the pipeline.

Flooding, and damage to power lines and fibre-optic cables caused by trees and forestry slash piling into bridges, were responsibl­e for many of the electricit­y and communicat­ions outages last year.

New Zealand Transport Agency Waka Kotahi can’t say whether the cyclone flushed out most of the loose trees and slash that caused so much damage or whether – like a penny-pusher game at the fair – a whole new bunch of “coins” have built up, ready to drop if given a further nudge.

Linda Stewart, its director of regional relationsh­ips for the central North Island, explains it doesn’t have oversight of “broader assessment­s of forestry debris and loose trees”.

But she says it has recognised the importance of clearing such debris as quickly as possible.

“An example of this was in November last year when wood debris was cleared from under State Highway 35’s Gladstone Road bridge following a storm,” she says.

“We continue to have a good working relationsh­ip with the forestry industry, and acknowledg­e the industry’s focus on mitigating risks in the event of future adverse weather.”

The problems caused by flood-borne debris appear to have been a wake-up call for telcos, including broadband network company Chorus, which have since built more resilience into their networks.

Telecommun­ications Forum chief executive Paul Brislen says hundreds of kilometres of fibre have been installed to replace damaged lines and provide extra back-up.

Some telcos have built “self-healing” capabiliti­es into their networks, he says.

If that sounds reminiscen­t of the discussion in the movie Brazil about an air-conditioni­ng unit supposedly fixing itself, the reality is a little less futuristic.

“The fibre is connected in loops so if the eastern side is down, all traffic routes via the west. It’s at the speed of light so the customers don’t notice at all,” Brislen says.

“Previously this would be done manually but now the automation is at a level where it kicks in straight away.”

The telco industry was at pains to point out last year that most cellphone sites that were knocked offline by Cyclone Gabrielle – 660 across the country – were cut off because of a loss of power, rather than damage to their own infrastruc­ture.

The only way to address that was to truck-in portable generators and diesel to the road-damaged regions.

One NZ, Spark and 2degrees have all “refreshed and expanded” their fleets of generators and now have additional units ready for use around the country, Brislen says.

“Batteries are all on a schedule to be replaced and upgraded, and members are also introducin­g better automated power management that enables them to turn off features during times of excess need so core services will last longer.”

Some telcos have invested in “mobile exchanges on wheels”, cutely nicknamed Meows, that have satellite connectivi­ty, to restore some service as quickly as possible after a disaster, he says.

In a possible game-changer for emergency communicat­ions, at least, all are planning to launch new services that should let ordinary smartphone­s send and receive text messages via satellite if customers are outside areas of normal coverage, including because of an outage caused by a natural disaster.

While One NZ has claimed an edge in this space because of its relationsh­ip with satellite-network giant Starlink, all three mobile operators have a track record of helping each other out and sharing their network capabiliti­es in emergencie­s.

The biggest single cause of power cuts during Cyclone Gabrielle was the flooding of Transpower’s Redclyffe substation in Hawke’s Bay.

Redclyffe was one of 12 “critical” substation­s across the country that the national grid operator had previously identified in a 2020 report as being at risk of flooding.

The challenge is that moving a major substation is a huge undertakin­g and Transpower needs approval from the Commerce Commission to make major capital investment­s, given it is a monopoly that passes its costs on to customers.

Before the cyclone, Transpower had been preparing to ask the commission for permission to spend money making “two or three” of the substation­s more resilient to flooding between 2025 and 2030.

But Cyclone Gabrielle has caused it to attempt to pick up the pace.

Transpower grid delivery manager Mark Ryall says that as an “interim measure” it has rebuilt its control room at Redcylffe and elevated it by two metres, so that is higher than the flood waters reached last year.

It is now finalising a broader plan for the Hawke’s Bay, alongside local lines company Unison, that will take into account the result of new modelling of flood risks and projected power demand, he says.

“We would expect to have an update for the Hawke’s Bay community in a few months.

“Ahead of that, we are aiming to meet

with key stakeholde­rs including mana whenua, councils, other infrastruc­ture agencies and local landowners.”

Work has also been going on at the other 11 at-risk substation­s, as well as another four that weren’t on that list.

“For some sites, improvemen­ts are already under way. For others we are undertakin­g further investigat­ion, and for others we are working constructi­vely with councils to develop longer term regional plans,” Ryall says.

“This includes projects at Kaiapoi and Stoke that will provide greater resilience against flooding.”

Transpower has scheduled a workshop at the end of the month to discuss options for its Edgecumbe substation “following ongoing engagement over the criticalit­y of this site to the region”.

The work is not cheap. A proposal Transpower submitted to the Commerce Commission in November asks for permission to spend $200 million on measures to improve resilience between 2025 and 2030, Ryall says.

“This is a mixture of hardening the grid and investing in readiness with portable equipment and spares.”

Transpower chief executive Alison Andrew told Parliament’s transport and infrastruc­ture select committee on Thursday she would be very interested to see how the commission handled that request.

“At the end of the day, it comes down to how New Zealanders are going to pay for it.

“The interestin­g learning we had in Hawke’s Bay is it not just ‘power being available’, but it’s water being available, fuel being available, road access and telecommun­ications – we all want to come together as critical services and how do we make sure that resilience is appropriat­e across all of those central services?”

Unison network manager Gaganpreet Chadha says Transpower’s emergency repairs have made the Redclyffe substation more resilient.

Three smaller substation­s owned by Unison itself were also damaged by floods last year and have been built back better during “temporary repairs” in part by elevating equipment, he says.

“Permanent reconstruc­tion of Unison’s flood-affected sites is in planning and will also be carried out using modern, modular and elevated design standards to ensure greater resilience.”

Chadha says regulatory reforms would help reduce the risk of localised power outages caused by the likes of falling trees.

Of the 240,000 homes that lost power because of Cyclone Gabrielle, about 67,000 were cut off because of falling vegetation, according to Electricit­y Networks Aotearoa.

It suggested in a submission to the Government in May that lines companies could take on more responsibi­lity for trimming trees in people’s gardens to ensure they didn’t encroach on power lines.

That would be in return for foresters and commercial landowners taking full responsibi­lity for vegetation on their own land.

Chadha says the electricit­y industry would like to see progress on updating the tree regulation­s, but appears under no illusions that will be easy.

“We understand this is a complex process involving property rights as well as commercial interests,” he says.

 ?? ?? Transpower chief executive Alison Andrew says she will be interested to see how the Commerce Commission handles its $200m spending request.
Transpower chief executive Alison Andrew says she will be interested to see how the Commerce Commission handles its $200m spending request.
 ?? JOHN COWPLAND/ALPHAPIX ?? Crews from Unison work to get power back to Napier in the wake of Cyclone Gabrielle.
JOHN COWPLAND/ALPHAPIX Crews from Unison work to get power back to Napier in the wake of Cyclone Gabrielle.

Newspapers in English

Newspapers from New Zealand