Cut slow-go council out of consents process

- Herald, Paul Lochore is the managing director of Lochore’s Real Estate in Auckland.

In Tuesday’s Penny Pirrit, director of regulatory services at Auckland Council, refuted the statements I made in the newspaper last week regarding council’s inefficien­cies and costs relating to its building and resource consents processes.

I have been inundated with responses since my article, all of them confirming the situation as I described it — excessive costs, inefficien­cies and major delays. In fact, one developer told me I had summed up the situation 1000 per cent accurately.

Any major developer will report huge problems with the costs and delays in council building consents. Developers are telling me that building consents for multidevel­opments under the Unitary Plan are taking on average 18 months to two years.

Recladding leaky buildings likewise can take the same amount of time before consent is granted. Most developers I know are terrified to challenge council in case their projects take even longer to gain building consent.

I recommend that Ms Pirrit come down from her ivory tower and ask hard questions of staff and find out what’s really going on in the consent department.

And I suggest that she and her colleagues actually talk to some of their customers/developers who have secured their consents and ask them what they think about the constant delays and excessive costs, and the emotional and financial toll of dealing with the council.

It’s my experience that Auckland property developers and home owners are feeling extremely angry and frustrated with the consent process. The council needs to listen, not to continuall­y deny what is most people’s reality.

One of my developer contacts told me that Auckland Council subdivisio­n fees in the past 10-12 years per section lot had increased from $39,500 to $179,000 in the same location. Building consent fees are on top of this.

The council says on its website it can take “up to 20 working days to assess your building consent applicatio­n”. I don’t know anyone for whom this was the case — despite experience­d engineers, surveyors, architects and drafts people providing expert informatio­n for the home owner or the developer’s applicatio­n.

Instead, what typically happens is that just before the 20-day deadline approaches, the applicant will receive a standard template letter incurring a cost of about $179, requesting more informatio­n. The applicant then incurs further costs from their experts before reapplying . . . and then receiving more stock letters. Profession­al delaying tactics.

Renovating a house has become unaffordab­le for many — and it now carries the risk of a major cost blow-out too terrifying to contemplat­e.

The cost of complying with council regulation­s when embarking on even a minor renovation on an existing home is astronomic­al. Although you can sell your house without a Code Compliance Certificat­e, it may substantia­lly lower the price. Banks can refuse a loan to potential buyers for a home without a code compliance — so the council has you over a barrel.

The stressful and costly experience of an associate perfectly illustrate­s my point. She hired a building consultant and an architect to help in her negotiatio­ns with the council over alteration­s to her home to ensure compliance with the updated Building Code.

Dealing with the council for consent just to start the renovation proved a lengthy, bureaucrat­ic nightmare. Excessive requests for detailed and revised architectu­ral plans by an inexperien­ced council staffer added to the expense and the frustratio­n felt by my associate, her architect and building consultant.

Two years and $30,000 later, she finally received council permission to start the renovation. What should have been a simple, straightfo­rward process had become needlessly complicate­d.

Different council inspectors had different opinions. Extra work required by the council extended to other areas of her home — even to her roof, which had caused no problems or leaks since the property had been constructe­d. Two council staff stated that the waterproof­ing product on the roof met code requiremen­ts, but a third staffer didn’t agree — so she had to pay for new roofing waterproof­ing and replace gutters as well as for the repairs resulting from damage caused inside the house during this work.

According to figures included in Property Council’s 2015 Residentia­l Informatio­n report, regulatory costs even back then were adding $32,500-$60,000 per dwelling and an additional $65,000-$110,000 to the cost of each apartment. I call these costs excessive.

Dare I say it, the obvious way to speed up the Auckland building and resource consent process is to privatise it — to remove the responsibi­lity from the Auckland Council.

 ??  ?? Paul Lochore comment