The New Zealand Herald

How to rebuild the constructi­on industry

- Derek Firth Derek Firth is an Auckland barrister specialisi­ng in constructi­on disputes.

Every prospectiv­e project owner and developer is now severely disadvanta­ged by the absence of a large pool of financiall­y strong contractor­s. This situation has been selfinflic­ted by themselves and their predecesso­rs.

It is often said risk allocation is inappropri­ate, and this is best illustrate­d with examples. It is irresponsi­ble for an employer to require a contractor to take all the risk in relation to ground conditions. Let the present claim for more than A$1 billion ($1.09b) against New South Wales Transport be a lesson to everyone, whether you are building an undergroun­d railway or a house, or something in between.

That claim is for damages for deceptive and misleading conduct in relation to undergroun­d issues. It seems to be an example of the consequenc­es of an owner trying to be too clever.

Also, it is irresponsi­ble of an employer to hold over the head of the contractor the right to give some work to others in the future, and it is irresponsi­ble to retain the right to make significan­t programmin­g adjustment­s yet deny a variation to the contractor.

These are simple examples of numerous situations where contractor­s are being regularly asked to take risks which they are not equipped to either manage or price.

Another common example is thrusting on to the contractor the risk of future design issues when the owner retains control of design.

There is an obsession with accepting the lowest price regardless of good reasons not to. There is an obsession about requiring tendering for every project when that is not always appropriat­e.

In Fletcher’s heyday, the company was well known within the constructi­on industry for two strategies. First, it went through a period of many years when it negotiated as many contracts as it could and avoided tendering wherever it could. This significan­tly reduced its risk, but it also ensured the employer ended up with a financiall­y strong and very reliable contractor. Secondly, it had a reputation in the industry for looking after its subcontrac­tors. They are the lifeblood of any major contractor.

It was not the fault of Fletcher that the opportunit­y to obtain negotiated work significan­tly fell away. It was probably due to the short sightednes­s (and

inexperien­ce) of those at the procuremen­t end who could not stand the thought of missing out on an alternativ­e contractor being a fraction cheaper.

Some of these issues are not only about owners and their consultant­s, but their bankers, and their consultant­s. They do not seem to understand it is better to pay a slightly higher price and have the security of a financiall­y sound contractor with a reputation for consistent quality workmanshi­p.

Some seem to think that shaving a few dollars off another contractor’s margin to enable it to secure the job will provide the best outcome.

This could not be more shortsight­ed and wrong.

Unfortunat­ely, consultant­s advising owners who wish to impose draconian contract conditions and shave the margins to the bare bone would rather assist them to implement these unwise tactics than see the owner shift to another consultant who will quickly accommodat­e their foolish requiremen­ts.

Although it is obvious to everyone in the industry, no one seems to want to believe that if the contract has been concluded on the basis of draconian contractua­l provisions, minimum margins and generally an over-riding anticontra­ctor approach, then what will happen is that the contactor will be on an attacking position from the outset.

It will want to preserve its margin and it will want to ensure it does not lose money as a result of the unfair provisions. It will therefore adopt a claims mentality from the outset.

The most effective solution will be a change in mindset.

Owners and their consultant­s will be likely to achieve the best results if they stand back from inappropri­ate procuremen­t tactics and take a broader view of getting the right contractor for the appropriat­e job at a fair price and based on fair conditions.

A mindset of saving a few dollars and imposing harsh conditions because they think that is how it should be done, will continue to not work.

Ironically, many experience­d employers and consultant­s have no difficulty with this and adopt good approaches. The problem lies with a number of less experience­d people coming into a busy market and wanting to prove themselves.

Another solution which can often require an enormous level of will power is to complete the design before tenders are called, or a contractor is asked to price the work. We are riddled with projects where owners are always trying to “beat the gun”. The fallacy with an obsession for always requiring tendering can be simply illustrate­d. Consider a project such as a hotel or apartment block which is likely to cost in the region of $80 million. That is not the amount which will avoid being tested in a negotiated contract. This is because usually about 80 per cent of it is competitiv­ely bid through the tendering for subcontrac­t work. Only about 20 per cent of that price is what is really being negotiated.

Good quantity surveyors will have a very accurate knowledge of the going rate for the various margins (on-site and off-site overheads and profit) and they will know if a contractor is underprici­ng or over pricing.

Obviously, if one decides to proceed with a negotiated contract it is essential to require agreement by a date which still leaves time to tender if agreement can’t be reached. All consultant­s (lawyers, architects, engineers, project managers and quantity surveyors) should stand up to their clients and explain to them why short cuts, harsh clauses and penny-pinching are counterpro­ductive in many ways.

 ?? Photo / 123RF ??
Photo / 123RF

Newspapers in English

Newspapers from New Zealand