The Northern Advocate

$75m to power up Karapiro station

Hydro system update akin to ‘moving from a record player to Netflix’

- Grant Bradley

Mercury Energy will this week sign a $75 million deal to revamp its ageing Karapiro power station as part of an overhaul of its Waikato River hydro system costing close to half a billion dollars.

The 70-year-old station will have its generators and turbines replaced by Austrian-based firm Andritz in a transforma­tion Mercury's executive general manager, hydro and wholesale, Phil Gibson, said was “like moving from a record player to Netflix”.

New equipment will allow the station to lift peak capacity by 17 per cent, sufficient to charge more than 6000 electric vehicles simultaneo­usly.

“When you're spending $75m to keep it going and for that money to find another 17 per cent more capacity, it's a triumph,” Gibson said.

The overhaul of the landmark station is the fifth on the nine-station Waikato system which generates about 10 per cent of the country's electricit­y and helped deliver record earnings last year after two years of strong inflows.

Gibson said overhaulin­g the total system could take close to two decades, funded off the balance sheet of Mercury, our third-biggest gentailer.

He said Mercury was privileged to own and operate the stations, the oldest of which, Arapuni, dated to 1929: “Our modernisat­ion programme brings the best of new design and manufactur­ing practices to these stations, in many cases replacing machinery that has operating for more than half a century.”

At Karapiro, the three units with generators and turbines weighing 250 tonnes will be lifted out and replaced over three summers, with . minimal disruption to generation.

“The project will also benefit the regional economy with an increase in personnel living near and working at Karapiro through various stages of the modernisat­ion.”

The Andritz Hydro contract is due to be signed this week after two years of scoping.

The project will increase overall peak station capacity by 17 per cent or 16.5MW, to 112.5MW — enough to power approximat­ely 19,000 New Zealand homes — and average energy production by 32GWh to 537GWh per year.

Constructi­on of the Karapiro power station started in 1940 during World War II.

Progress was impacted by warrelated labour and materials shortages.

It was completed in 1947 and commission­ed in 1948.

Lake Karapiro was formed behind the dam and is now well used for rowing and waka ama regattas.

Andritz Hydro has installed more than 30,000 turbines (generating 420,000 MW) around the world.

Other significan­t Waikato River projects Mercury has completed include upgrades at Ohakuri and Arapuni and to come are two larger projects, similar in scale to the Karapiro project, under way at Whakamaru and Aratiatia with completion expected in the mid-2020s.

The major work was done in summer when demand was lowest.

Tight supply with gas outages and low lake levels pushed up spot prices last year and Transpower asked generators to avoid maintenanc­e work this May and June so it could maintain a sufficient capacity buffer during peak winter demand.

The national grid operator has highlighte­d two dates in mid-May when a combinatio­n of planned power station outages and transmissi­on work could leave that margin lower than it would like, should one of the big North Island thermal plants drop out of the system at peak time.

Last week Mercury said high spot prices in the December quarter should enable it to meet its full-year earnings guidance despite lower hydro production and the loss of earnings from a meter business which was soon to be sold.

The firm reiterated its September forecast for $515m of operating earnings in the year to June.

That was despite the company also lowering its full-year hydro generation assumption by 50 gigawattho­urs to 4150 GWh due to low inflows into its Waikato catchment since October.

The sale of the Metrix business, announced last month and scheduled for March 1, would also reduce earnings before interest, tax, depreciati­on and changes in financial instrument­s by about $10 million, the company said.

For that money to find another 17 per cent more capacity, it's a triumph.

Phil Gibson, Mercury

Newspapers in English

Newspapers from New Zealand