The Northern Advocate

10 years of SH1 roadworks

$692m four-laning project carried out with extensive constructi­on work under way

- Susan Botting Local Democracy Reporter

Northlande­rs are facing 10 years of State Highway 1 roadworks south of Whanga¯ rei as the highway’s new $692 million four-laning takes shape.

Steve Mutton, NZ Transport Agency (NZTA) director regional relationsh­ips Northland and Auckland, said four-laning constructi­on on the Whanga¯rei to SH1’s Port Marsden turnoff would be completed by 2027 or 2028.

Four-laning constructi­on on the 22km route would begin early 2024, Mutton told Wednesday’s Regional Transport Committee (RTC) meeting in Whanga¯rei.

“Four-laning’s going to take a number of years to complete,” Mutton told the meeting.

That constructi­on start will come on top of soon-to-be-started safety improvemen­t constructi­on work along the same stretch of road and extending south to Wellsford.

It comes on top of the almost a year’s roadworks at the Otaika Loop Road/SH1 roundabout that started in March 2019.

And it adds to Tarewa Rd/SH1 intersecti­on roadworks that began in Whanga¯rei city in 2018.

Mutton told the Regional Transport Committee (RTC) meeting NZTA was putting together the initial planning and business case for the new four-laning project. This would be completed before the end of the year.

The four-laning work will go out to tender in mid-2021. Contracts will be let in mid-2023. Roadworks will begin in mid-2023 or early 2024. The new corridor’s route will be identified through developing the project’s business case.

RTC member and Northland Regional Council councillor Rick Stolwerk said it was important NZTA clearly communicat­ed about the decade’s roadworks to Northlande­rs and others using affected parts of SH1 faced.

Mutton said the Whanga¯rei to Port Marsden four-laning came in conjunctio­n with other constructi­on work progressin­g northward towards Northland’s biggest city along the more southern sections of the Whanga¯ rei to Auckland highway.

The Puhoi to Warkworth section of these works would be completed by the end of 2021.

The Warkworth to Wellsford section of the route was progressin­g. The NZTA website says resource consent applicatio­ns for this section will be lodged next month.

The Whanga¯rei to Port Marsden four-laning is part of highway constructi­on and roadworks improvemen­t along the full length of the road from Whanga¯rei to Auckland.

RTC chairman John Bain said the just announced $692 million fourlaning from Auckland to Port Marsden was to be commended but wasn’t the full picture.

He called for completion of fourlaning along the full length of SH1 between Whanga¯rei and Auckland Harbour bridge.

“In reality, the plan we have is only half a pyramid,” Bain told the meeting.

“It’s pointless to have four laning bottleneck­s each way on the remaining two-laned section of SH1. “We would like to see the plan for completion of the route to Te Hana [from Northland’s side] and have the Auckland Council side meet up there,” Bain said.

He said it was important to have confirmati­on of the fourlaning right through from Whanga¯rei to Auckland — even if its timeframe was as far out as 2035.

“We need to know the plan in place. We know Rome wasn’t built in a day, it will happen,” Bain said.

Meanwhile, Bain called on NZTA to notify the community about where new parts of the route from Whanga¯rei to Auckland would be.

He said three possible “lines on paper” had been presented in 2017.

“All that’s done is make people very unsure about which farm the road’s going through,” Bain said.

“If we can get proposed route on paper, people will know where it’s going to be,” Bain said.

He called for the route’s section which currently traverses the Brynderwyn­s to be bypassed.

At $56 per vehicle to traverse the Brynderwyn­s, it was too expensive for trucks. He said the Brynderwyn­s should not be part of the main SH1.

An alternate route, even with a minimal toll, would be preferable for trucks.

Ann Court, RTC member and Far North District deputy mayor, said it was important the new work resulting from recent Government funding into the region didn’t compromise existing business-as-usual work that had been committed to.

“You’ve said it wouldn’t compromise business as usual, but you’ll still have to hire roading engineers, planners, contractor­s. I’m concerned about the business as usual impact on projects around Northland and New Zealand from Government­funded work around Northland and New Zealand,” Court told Mutton at the meeting.

“What tangible tool can we use [to make sure that doesn’t happen]?”

Greg Martin, RTC member and Whanga¯ rei District Council councillor and the council’s infrastruc­ture committee chairman, said Infrastruc­ture New Zealand’s board had assured him during its recent visit to Whanga¯rei there was adequate resourcing available to bring the roading to life.

 ??  ??
 ?? Photo / File ?? Northlande­rs are facing 10 years of roadworks on SH1 south of Whanga¯ rei as the new highway takes shape.
Photo / File Northlande­rs are facing 10 years of roadworks on SH1 south of Whanga¯ rei as the new highway takes shape.
 ??  ?? Steve Mutton
Steve Mutton
 ??  ??

Newspapers in English

Newspapers from New Zealand