$15m upgrade to scheme expected to be completed in 2022-23 season

-

The $3 million third stage of improvemen­ts to the Awanui flood scheme is progressin­g well, according to the Northland Regional Council. Councillor Colin Kitchen, the regional council’s Te Hiku representa­tive, said the third annual constructi­on season of the $15m scheme upgrade was now expected to be completed in 2022-23.

About $1.1m worth of work had been done last constructi­on season, but a subsequent multimilli­on-dollar injection from the Government as part of its Covid-19 recovery response package was allowing the project to be completed more quickly and at less direct cost to ratepayers.

This constructi­on season’s schedule was costing about $3,050,000, including extensive earthworks for southern spillways under way over about 2.4ha of former farmland behind Rongopai Place, in Kaitaia, including constructi­on of 280m of new stopbanks to better protect 29 floodprone homes in Rongopai Place, and about 900m of new spillway.

Kitchen said the $1.1m spillway work would account for more than a third of this season’s programme, and was now 90 per cent complete, although the spillways would not be used for the next year or two, to allow grass to become well-establishe­d.

Church Rd scour protection and stopbank stabilisat­ion was about 60 per cent complete, and work at Allan Bell Park was about 10 per cent complete.

The weather-dependent constructi­on season typically ends in May, but timber had been ordered for constructi­on of the Milky Way floodwall, near the SH1 Waikuruki Bridge, which could progress irrespecti­ve of wet weather.

In an additional community benefit, some of the excess fill had been used to improve the nearby A&P showground­s and equestrian track.

The council also has $4m of work scheduled to begin late this year for the new 2021-22 constructi­on season, and another $5m, which should mark the completion of the upgrade, for the year after that.

Kitchen says the upgrade was designed to help future-proof the decades-old scheme, including predicted climate-change impacts, as well as delivering a considerab­ly higher level of protection for Kaitaia and surroundin­g areas.

“The upgrade collective­ly is designed to protect urban Kaitaia in a once in a century-type flood and a 1:20-year event in surroundin­g rural areas,” he said.

Already Northland’s most common natural hazard, flooding would likely become more intense as climate change continued, increasing risks to communitie­s in flood-prone areas and to critical infrastruc­ture.

“One of the key drivers for the Awanui scheme upgrade is to make sure we’re collective­ly doing as much as we can now to prepare and adapt for what the future is predicted to hold,” he added.

The council had warned that without the added protection offered by the upgraded Awanui scheme, a large flood in urban Kaitaia could cause tens of millions of dollars’ worth of damage and put lives at risk.

 ?? Photos / NRC ?? A new stopbank takes shape behind Rongopai Place, Kaitaia.
Photos / NRC A new stopbank takes shape behind Rongopai Place, Kaitaia.