The Northern Advocate

Rail repairs tracking well

Sole Auckland line now on track to reopen mid-year

- Denise Piper

Repairs on the stormdamag­ed sole railway between Northland and Auckland are progressin­g, and a reopening date has been set for the middle of the year.

The North Auckland Line has been closed by slips since the end of January 2023, when the region was hit by the Auckland Anniversar­y floods. Cyclone Gabrielle compounded damage to the line.

In all, there were 220 slips along the 180km line from Swanson in west Auckland to Whangārei, including 33 major slips.

While work has been progressin­g on repairing all the damage, KiwiRail was previously unable to give a reopening date.

But good progress means civil works are set to be complete in the next few months, followed by testing, with the aim of a mid-year reopening, Northland rail upgrade programme director Eric Hennephof said in KiwiRail’s latest newsletter.

While the railway has been closed, KiwiRail has also upgraded the line from Whangārei to Kauri to take heavier, 18-tonne trains. It has also upgraded the Whangārei rail yard for greater freight volumes and fewer flood risks.

The line upgrade — completed from Swanson to Whangārei just days before the severe weather hit — will allow the line to run the same locomotive­s as used in the rest of the North Island and to run longer trains, Hennephof said.

In the newsletter, he thanked everyone for their patience, especially rail customers.

“We remain committed to reopening the North Auckland Line and making sure it can better stand up to future weather events,” he said.

But rail proponent Alan Preston, from Save Our Rail Northland, said it would have been useful to have more details from KiwiRail about the closure, such as a map of where the slips were located.

He was concerned the long closure of the railway benefited road-based freight, which had opportunit­ies in the face of no competitio­n.

Preston said rail needed to be prioritise­d as a transport alternativ­e in New Zealand, which is the world’s most car-dependent nation and relies on importing millions of dollars of petrol each day — a supply chain that is not only vulnerable but produces about 17 per cent of the country’s greenhouse gases.

“This is a perilously irresponsi­ble and dangerous way to plan a remote island nation’s infrastruc­ture,” he said.

But Whangārei mayor Vince Cocurullo said both road and rail were important in Northland’s infrastruc­ture.

He sees a four-lane highway between Auckland and Whangārei as a high priority as the highway would deal with the majority of traffic, even once a railway connection to Marsden Point was built.

“Right now, the four-laning is desperatel­y needed.”

But Cocurullo said rail was also important for heavy traffic and large volumes, and he believed KiwiRail had made steady progress on repairing the line.

Many people did not realise how difficult it was to fix a slip on rail line that needs to be perfectly level, as opposed to a road, which can have more give, he said.

KiwiRail’s latest update revealed some of the difficulti­es involved with the upgrade, including access to the slip sites, as contractor­s had to rely on long road trips because of the rail line being out of action.

Working around native bush was another difficulty; KiwiRail engaged ecologists, erosion control specialist­s and the Department of Conservati­on to ensure native flora and fauna were protected.

In late December, the team had to work around a kāhu (swamp harrier) nest in dense grass close to the rail line near Wellsford, the newsletter said.

Marsden Pt link out of steam?

While $40 million from the Provincial Growth Fund was set aside to buy land needed for a rail link to Northport at Marsden Pt, a business plan for its constructi­on has still not been approved.

In the October 2023 hearing into Northport’s expansion, KiwiRail’s David Gordon said 73 per cent of the land needed to build the line had been bought, excluding iwi land, the coastal marine area and port land.

Engineerin­g and geotechnic­al design had been funded to help inform the business case, but he admitted key issues were yet to be decided, that had an impact of hundreds of millions of dollars.

Examples of the key issues included whether cut material could be used as fill elsewhere, and what height the corridor should be built relative to flood levels and assumed sea level rise.

 ?? ?? The upgrades to the North Auckland Line include an 8m-deep excavation near Ranganui, Kaiwaka, where 21,000cu m of unsuitable, saturated soil had to be excavated and will be replaced with more suitable foundation­s.
The upgrades to the North Auckland Line include an 8m-deep excavation near Ranganui, Kaiwaka, where 21,000cu m of unsuitable, saturated soil had to be excavated and will be replaced with more suitable foundation­s.
 ?? ?? The upgrades to the North Auckland Line including working around a kāhu (swamp harrier) nest, found near the line in Wellsford in December.
The upgrades to the North Auckland Line including working around a kāhu (swamp harrier) nest, found near the line in Wellsford in December.

Newspapers in English

Newspapers from New Zealand