The Post

Water repair costs triple

- Tom Hunt

The cost to fix a leak has more than tripled as Wellington Water, sitting on an 800-leak backlog, tells the city council to hurry up on another $1 million.

Wellington Water, a water utility owned by councils in Wellington, Hutt Valley, Porirua and South Wairarapa, asked the Wellington City Council in December for an extra $2m to fix its leak backlog.

It was granted an additional $1m with an extra $1m if it met goals.

Now a report to the council shows a backlog of 74 leaks had been fixed at a cost of $365,000.

But the backlog has grown from 800 to 806 because more leaks have been added to the need-to-be fixed list.

At $4932 per leak, that works out more than triple the 2021 average per leak of $1500, which was then raised to an estimated $3000 by October 2023, according to a recent report to council.

A dry summer mixed with decades of underinves­tment in pipes means the areas covered by Wellington Water are currently under a sprinkler and irrigation ban with the chance of a ban on all outdoor use now at 43%.

In February, it was estimated that 44% of the region’s drinking water was lost to leaks. Wellington Water first said getting plumbers to fix leaks was not feasible but in February it did a U-turn saying it was open to the idea.

However, in an email to councillor­s, council waste, water, and resilience manager Chris Mathews said work to get Wellington Water to do this was “progressin­g at a glacial pace”.

Councillor Ben McNulty said the expectatio­n of the $2m December funding boost was that 800 leaks would be fixed at an average cost of $2500 a leak.

Wellington Water was meeting with councillor­s tomorrow and McNulty said, without some good answers about why the backlog wasn’t being properly addressed, he would call for the remaining $1m to go towards the council directly employing plumbers to clear the backlog.

Wellington Water acting chief executive Keith Locke said the water utility fixed 399 Wellington City leaks in February – but just 74 from the funding boost. The programme could not start until January 29 due to the Christmas break and time for planning and setup.

It tried to use the money “as quickly as possible” but it needed to find available contractor­s.

“Unfortunat­ely, we cannot simply turn on this type of work overnight,” he said.

The quick ramp-up also led to higher costs as “a result of the leaks being more complex and the fact that we’ve had to rely solely on external contractor­s”.

“Unfortunat­ely, we cannot simply turn on this type of work overnight.” Keith Locke

Wellington Water acting chief executive

It was estimated the first $1m would be used by the end of April but Wellington Water needed to know by March 22 whether the second $1m would come or “we will have to let our contractor­s go”, Locke said.

Councillor Tim Brown and Iona Pannett were the only two councillor­s to vote against the extra $2m.

“There is a fundamenta­l issue with accountabi­lity, which has not in any way been addressed by the short report they have now provided,” Brown said yesterday.

“More money seems to have far more effect on the cost of each fix than on the number of fixes.”

Pannett said there needed to be more accountabi­lity, and Wellington Water “needs to pick up the pace”.

Mayor Tory Whanau said the new Wellington Water figures were “disappoint­ing” and showed the water utility needed “stronger reporting and accountabi­lity measures”.

The council was working with other councils on a new model for councilcon­trolled organisati­ons, of which Wellington Water was one.

Newspapers in English

Newspapers from New Zealand