Water repair costs triple
The cost to fix a leak has more than tripled as Wellington Water, sitting on an 800-leak backlog, tells the city council to hurry up on another $1 million.
Wellington Water, a water utility owned by councils in Wellington, Hutt Valley, Porirua and South Wairarapa, asked the Wellington City Council in December for an extra $2m to fix its leak backlog.
It was granted an additional $1m with an extra $1m if it met goals.
Now a report to the council shows a backlog of 74 leaks had been fixed at a cost of $365,000.
But the backlog has grown from 800 to 806 because more leaks have been added to the need-to-be fixed list.
At $4932 per leak, that works out more than triple the 2021 average per leak of $1500, which was then raised to an estimated $3000 by October 2023, according to a recent report to council.
A dry summer mixed with decades of underinvestment in pipes means the areas covered by Wellington Water are currently under a sprinkler and irrigation ban with the chance of a ban on all outdoor use now at 43%.
In February, it was estimated that 44% of the region’s drinking water was lost to leaks. Wellington Water first said getting plumbers to fix leaks was not feasible but in February it did a U-turn saying it was open to the idea.
However, in an email to councillors, council waste, water, and resilience manager Chris Mathews said work to get Wellington Water to do this was “progressing at a glacial pace”.
Councillor Ben McNulty said the expectation of the $2m December funding boost was that 800 leaks would be fixed at an average cost of $2500 a leak.
Wellington Water was meeting with councillors tomorrow and McNulty said, without some good answers about why the backlog wasn’t being properly addressed, he would call for the remaining $1m to go towards the council directly employing plumbers to clear the backlog.
Wellington Water acting chief executive Keith Locke said the water utility fixed 399 Wellington City leaks in February – but just 74 from the funding boost. The programme could not start until January 29 due to the Christmas break and time for planning and setup.
It tried to use the money “as quickly as possible” but it needed to find available contractors.
“Unfortunately, we cannot simply turn on this type of work overnight,” he said.
The quick ramp-up also led to higher costs as “a result of the leaks being more complex and the fact that we’ve had to rely solely on external contractors”.
“Unfortunately, we cannot simply turn on this type of work overnight.” Keith Locke
Wellington Water acting chief executive
It was estimated the first $1m would be used by the end of April but Wellington Water needed to know by March 22 whether the second $1m would come or “we will have to let our contractors go”, Locke said.
Councillor Tim Brown and Iona Pannett were the only two councillors to vote against the extra $2m.
“There is a fundamental issue with accountability, which has not in any way been addressed by the short report they have now provided,” Brown said yesterday.
“More money seems to have far more effect on the cost of each fix than on the number of fixes.”
Pannett said there needed to be more accountability, and Wellington Water “needs to pick up the pace”.
Mayor Tory Whanau said the new Wellington Water figures were “disappointing” and showed the water utility needed “stronger reporting and accountability measures”.
The council was working with other councils on a new model for councilcontrolled organisations, of which Wellington Water was one.