The Press

Contractor dumped from hospital project

- JACK FLETCHER

A man behind a firm contracted to work on Christchur­ch Hospital’s new acute services building says his business is ‘‘finished’’ after the contract was cancelled with two days’ notice.

Troy Lange, director of Grace Developmen­t 2008 Ltd, said the project had been plagued by delays.

Grace Developmen­t was contracted to install wall boards on three levels of the new building, which would provide services for patients needing to recover from surgery or short-term treatment for severe injuries, illness, or urgent medical conditions.

Lange said the company had completed about $850,000 worth of work. Its contract was worth $3 million.

Lange was sent an email from CPB Contractor­s on Saturday saying Grace Developmen­t’s access to the site had been revoked. In a meeting on Monday, the company’s contract was cancelled.

‘‘It’ll finish us. We will go into liquidatio­n,’’ he said.

‘‘I have a young family, three young kids. I’m fighting for my family now – it’s just not right.’’

Lange laid off his five staff and told his 20-or-so subcontrac­tors ‘‘they’ve got no work’’.

‘‘They were pretty good about it, but I could hear in their voices they were wondering what they were going to do.’’

CPB’s email cited quality, safety and resource issues as the reason for the contract cancellati­on.

The email said Grace workers were wearing short-sleeved shirts when long-sleeved were required.

It also said Grace did not have sufficient staff on site to complete the contracted work and some work had been finished to a poor standard.

CPB ignored The Press’ repeated requests for comment.

Lange refuted CPB’s claims and said Grace Developmen­ts should have already completed its assigned work, but ‘‘the engineers are not getting the mark-offs through to us quick enough’’.

‘‘We’ve been doing the work as quick as we can, but … they say ‘Here are some sign-offs, we need you on that tomorrow’ – that just can’t happen.

‘‘They need to give us the workload a month in advance, [so] we can say ‘We need this much resource, we’ve got this signed-off work’, and we can say to our guys around town, ‘Here is actual signed-off work’.’’

Lange said Grace’s contractor­s and others were avoiding work at the site.

‘‘People have heard about the hospital – that it’s a fight and a struggle getting the work signedoff – and [they] don’t want to go near it, so we’ve struggled to get people to work there.’’

The Press asked the CPB project manager who Lange reported to if engineer sign-offs were to blame for any potential project delays and what the project’s expected completion date was.

He was also asked if contractor­s were avoiding work at the site because of a struggle to get work signed-off.

The project manager did not respond to emails or phone calls.

Ministry of Health critical projects director Michael Hundleby said he could not comment on the claims as it was a contractua­l matter between CPB and Grace Developmen­ts.

Delays for such a large project were not unusual and had been ‘‘factored into the planning’’, he said.

The Hospital Redevelopm­ent Partnershi­p Group was satisfied the project was on-track for completion at the end of 2018, as contracted.

In August, CPB Contractor­s was selected to design and construct the Christchur­ch convention centre, another embattled project beset with delays.

 ?? PHOTO: STUFF/STACY SQUIRES ?? Troy Lange, director of Grace Developmen­t contractor­s, has had his $3 million acute services building contract cancelled.
PHOTO: STUFF/STACY SQUIRES Troy Lange, director of Grace Developmen­t contractor­s, has had his $3 million acute services building contract cancelled.

Newspapers in English

Newspapers from New Zealand