The Press

Bid to keep Town Hall budget blowout quiet

- Nick Truebridge nick.truebridge@stuff.co.nz

The budget for the delayed Christchur­ch Town Hall project has blown out to more than $152 million – and the city council tried to cover up the latest increase.

Three years ago the Christchur­ch City Council told ratepayers they ‘‘did not expect’’ to pay more than the original

$127.5m restoratio­n cost.

But councillor­s met in secret last week to discuss the latest

$12m top-up, which takes the total budget to $152.2m, after it already ballooned to $140.6m. Mayor Lianne Dalziel and senior council staff agreed to answer questions on the blowout after the informatio­n was leaked to The Press. A public-excluded council meeting agenda showed it was proposed to keep the bust private until December 2019, when the project was due for completion and the full cost would be clear. Council major facilities capital delivery manager Alistair Pearson confirmed the increase to $152.2m and said extra costs would fall on the council.

‘‘It’s been an evolutiona­ry process right through, so as we peel back the layers we find issues, we find concerns, then we then action those concerns and expend money,’’ he said.

‘‘There are other elements where we said ‘If we did these functional­ity improvemen­ts now, would that be the right time to do them?’.’’

The council ‘‘added in’’ new features such as the wind lobby and improved acoustics, the conference room and the upper levels, he said.

The wind lobby was an addition similar to the city council building’s Hereford St entrance. The new Christchur­ch Symphony Orchestra rehearsal facility had also contribute­d to extra costs, Pearson said.

Dalziel suggested some major spending decisions were made without councillor approval.

‘‘Generally speaking, I think people (councillor­s) were disappoint­ed it was coming in over what had been budgeted for and how close that informatio­n became available to a decision [on the increase] being required,’’ she said. ‘‘There were clearly decisions that had been taken

along the way that hadn’t been through a proper formal process.

‘‘I’ll mention the fly tower . . . because that was a substantia­l sum of money . . . that wasn’t formally signed off by council, so I’m also disappoint­ed about that.’’

A fly tower is a backstage system that controls sets and other components of shows.

However, Dalziel did not regret approving the restoratio­n.

‘‘What I’m always reminded of is if we’d gone down the pathway of building a new auditorium it would’ve cost a lot more.’’

Former Rebuild Minister Gerry Brownlee, who was not convinced the hall was worth restoring, said he was ‘‘not surprised at all’’ to hear about the budget blowout.

‘‘Firstly, the concern we had was just how challengin­g the land was, because it didn’t have the greatest of geotech recommenda­tions on it,’’ he said. ‘‘The Town Hall decision was a nostalgic one; you know, it might work, it might not. I won’t make a comment about that, but I’m not surprised it’s cost more.’’

Council customer and community general manager Mary Richardson said it was possible the final cost of the project might be less than $152.2m.

Extra costs would not have an impact on rates and would be found within existing budgets.

Meanwhile, changes have been made to the restoratio­n, including adding two council general managers to the project steering group.

‘‘We are looking closely at the way we run all the projects in the future,’’ Richardson said.

‘‘There were a lot of variations made and were a lot of things that we’re still waiting for final prices on, so there was potential for the price to go up as decisions were being made.’’

 ?? DAVID WALKER/STUFF ?? Progress on the Christchur­ch Town Hall in the central city which is due to be completed in December next year.
DAVID WALKER/STUFF Progress on the Christchur­ch Town Hall in the central city which is due to be completed in December next year.
 ??  ??

Newspapers in English

Newspapers from New Zealand