The Press

Intersecti­on upgrade delayed

- Kim Nutbrown

The completion of a $960,000 upgrade to a busy Kaiapoi intersecti­on has been delayed after problems were found with a new water main.

Smith St has been a hub of constructi­on activity for the past eight months while Waimakarir­i District Council contractor­s upgraded the intersecti­on with Williams St.

The work included the installati­on of a new roundabout, central islands and four intersecti­on splitter islands.

There have also been kerb and channel upgrades, and new stormwater, sewer and water pipes have been installed.

The project will take an extra month to complete after the way a water main was installed caused the shoulder of the road to subside.

Council roading manager Joanne McBride said it was unfortunat­e the work had to be redone, but it was important to get it right.

‘‘While the majority of work went as planned, an issue with the installati­on of the water main was identified during constructi­on, resulting in the need to repair an area where the ground has subsided between Williams St and Princess Pl,’’ she said.

McBride said it was not uncommon for issues to be identified post-constructi­on.

The repairs – which involve digging a 1.5 metre to 2m-wide trench – are being completed by the contractor­s at no extra cost to ratepayers.

Part of Smith St has been cordoned off while the repairs are carried out.

McBride said the council would do as much as it could to minimise disruption to nearby homes. Access to driveways will be restricted at times, but will be restored by the end of each day.

On-street parking is also affected, and traffic management will be in place with signs and temporary speed restrictio­ns until the work is finished.

‘‘We would like to thank residents in the area for their patience while the final work is completed,’’ McBride said.

Newspapers in English

Newspapers from New Zealand