The Press

Work held up as firm went bust

- Lee Kenny lee.kenny@stuff.co.nz

Rebuild work at a Christchur­ch school – which was already behind schedule – was further delayed when the constructi­on firm went bust, owing more than $5 million.

Christchur­ch-based Corbel Constructi­on went into liquidatio­n in December 2018, owing $4.5m to unsecured creditors, $266,000 to BNZ and $960,000 to a private trust.

The company was partway through the first stage of Opawa School’s post-quake redevelopm­ent at the time. The project – which included new teaching spaces and an administra­tion area – was originally scheduled for completion by September 2017 but did not finish until June 2020, at a cost of $4.5m.

Corbel Constructi­on was founded in 2000 and employed around

80 fulltime staff.

It secured several Ministry of Education contracts as part of the Christchur­ch Schools Rebuild Programme, including $5m for Shirley Primary School’s refurbishm­ent and $2.2m for the constructi­on of a classroom block at Tai Tapu School.

It was also chosen to deliver the

$16m upgrade for North Canterbury schools, expanding or improving facilities at Oxford Area, Rangiora Borough, Ashgrove and Southbrook schools.

Head of education infrastruc­ture service Kim Shannon said the ministry was made aware of the firm’s liquidatio­n at the time, and Opawa School was kept ‘‘fully informed’’. ‘‘The project was delayed by about five months while a replacemen­t contractor, Contract Constructi­on, was appointed,’’ she said.

Sally Ormandy, principal of Opawa School, said they were continuing to work with the ministry to complete their remaining building work.

One hundred and eleven greater Christchur­ch schools damaged by the earthquake­s are being replaced or repaired over 10 years as part of a $1.3 billion education rebuild programme.

A Stuff investigat­ion in October revealed that at least 18 school developmen­ts, which should have finished, have yet to have started.

Despite the delays, Education Minister Chris Hipkins said he was confident the project would be completed on schedule.

At Christchur­ch Girls’ High School, the constructi­on of the main block will move into the design phase in the new year after the ministry backtracke­d on its original decision to renovate the building.

Repairs were expected to cost about $27m and, as of October 1, 2020, just over $7.5m had been spent before work came to a standstill in April 2019. It is not yet known what the budget will be for the new developmen­t.

However, informatio­n released under Official Informatio­n Act shows the cost of the original plan increased by 50 per cent.

Newspapers in English

Newspapers from New Zealand