The Press

Rebuild under scrutiny as costs soar

- Will Harvie

Antarctica New Zealand is racing to reduce its Scott Base redevelopm­ent, even as the coalition Government has signalled the rebuild budget could be cut amid “serious concerns” about the project.

Yesterday, Antarctica NZ was working to keep the project within a $498 million budget, with the funds already being held by the organisati­on, chief executive Sarah Williamson said.

But Antarctica NZ may get only the “budget that was originally agreed” – or $262m – foreign affairs minister Winston Peters told Parliament on December 7.

A Treasury spokesman confirmed to The Press yesterday that Cabinet have the power to take allocated funds back.

Also speaking yesterday, a spokesman for Peters said, “Decisions relating to the project and its current budget envelope require further detailed policy work and Cabinet decisions.”

The coalition Government had “serious concerns” about the Scott Base redevelopm­ent and was looking into the “situation with urgency”, Peters said.

“We also have questions around Antarctica New Zealand's management of the project,” Peters said. There had been ”terrible waste“.

In late February, Peters announced that Antarctica NZ board chairperso­n Sir Brian Roche had resigned, and been replaced by entreprene­ur, diplomat and one-time McMurdo Station kitchen hand Leon Grice.

Heather Simpson – Helen Clark’s long-time top adviser – was also appointed to the board to fill a vacancy.

“These appointmen­ts are one of a series of remedial steps that the Government is taking to bring the project under control,” Peters said.

The fracas comes as the coalition Government has asked department­s to slash costs, layoffs have hit ministries, school lunches have been cut and other austeritie­s imposed.

By last September, Antarctica NZ had concluded it couldn’t build a base for $498m and commission­ed a working group of external and internal experts to consider options.

Its heavily redacted report was released by Antarctic NZ last week and the preferred option appeared to be reducing the number of new buildings at the base from three to two, while also repurposin­g the most modern building at the base, called the Hillary Field Centre. It was built in 2005 and upgraded in 2016.

Other parts of the base date back to the 1970s and 1980s.

The working group also considered flat-packing components into containers for shipping to Antarctica, using traditiona­l building practices at the site or having the base built overseas.

In December, the Antarctica NZ board asked for some of these ideas to be refined and costed to ensure “they are within the overall project budget as agreed in Budget 2023” - or $498m.

In Parliament in December, Peters was answering patsy questions put by one of his backbenche­rs about Scott Base.

Peters was ready with answers and rhetoric. He twice used the language about the “originally agreed” budget. He put his boot into the former Labour Government, which couldn’t “run a corner dairy” and doubled Antarctica NZ’s budget “just like that”. When announced in 2019, the budget was $262m, Peters said. The Labour-NZ First Government agreed to contribute about $200m and Antarctica New Zealand was expected to raise about $50m itself.

The pandemic and soaring constructi­on costs led the Labour Government to increase the budget

to $344m in 2021 and an additional $154m was added in 2022. Along the way, the fundraisin­g was dropped.

About $81m had been spent to June 30, 2023, and more since, on design of the new base, enabling works at the site, relocation of science experiment­s, and large purchases such as heavy plant and wind turbines, Williamson said. “This is a technicall­y complex project,” she said yesterday. “Antarctica is one of the most extreme and remote environmen­ts in the world. The ‘Antarctic factor’ adds considerab­le costs to the project that you would not see in a New Zealand build.”

An upgraded wind farm had also been added to the project, she said.

Few doubt that New Zealand must have some sort of base in Antarctica.

“New Zealand's polar science is held in very high regard around the world [and] in a global warming world we need polar science like we've never had before,” said Colin Monteath, who has worked across Antarctica for 32 seasons, 10 at Scott Base. “The bottom line is we have to have a good science hub, which can still be spartan,” said the author of a new book on Mt Erebus. They should just be making better use of the buildings they’ve got,” said Lars Brabyn, a University of Waikato geographer who has visited Scott 10 times.

The Hillary Field Centre is a “perfectly good building” that would end up in a Christchur­ch landfill if the original plan was carried out.

Antarctica NZ is not the only polar nation facing base redevelopm­ent problems. Before Covid, the US Antarctic Program planned to demolish dozens of buildings at McMurdo Station, a few kilometres from Scott Base, and replace them with six large structures up to three stories high.

The budget was US$400m (NZ$615m) and another US$200m was probably needed.

Post Covid, that’s been dialled back to a new accommodat­ion hall and a vehicle maintenanc­e building. Meanwhile, a constructi­on project at the American base at the South Pole was dropped entirely.

 ?? ?? The three-building design of the redevelope­d Scott Base may not survive scrutiny from the coalition Government.
The three-building design of the redevelope­d Scott Base may not survive scrutiny from the coalition Government.

Newspapers in English

Newspapers from New Zealand