The Southland Times

17 years and still counting for hall

- JO MCKENZIE-MCLEAN

ACromwell memorial hall project has been under way for 17 years and cost $478,000 with nothing to show.

The length of time and cost of Cromwell’s Memorial Hall project has been examined by Australasi­an management consulting firm Morrison Low and will be discussed at the Central Otago District Council’s audit and risk committee on October 24.

In a report presented to a Cromwell Community Board workshop on September 28, Morrison Low raised concerns about the length of time the project had taken without tangible results and implicatio­ns from a risk management perspectiv­e.

The Cromwell Memorial Hall Project has been under way for 17 years with significan­t analysis and profession­al advice sought, including seven reports prepared to date, the report says.

The community board has been involved in the process continuous­ly and reconfirme­d the preferred approach to the refurbishm­ent of the Memorial Hall several times.

Numerous consultati­on and community engagement processes have also been undertaken, including two focused consultati­on exercises.

The project was thrown a curve ball after the local body elections last year when new board member Robin Dicey put forward a newbuild option rather than a refurbishm­ent. It was proposed to be as a combined design build project.

In April, Dicey put forward a notice of motion to suspend work on the hall until a new-build option was investigat­ed.

Any changes to the scope and levels of service proposed will need to be consulted on and will have time and cost implicatio­ns, the report says.

‘‘There is the risk that it will reconfirm the current refurbishm­ent approach but with the delay of two years and significan­t additional costs.’’

The report made several key observatio­ns including:

Council has spent in the order of $478,000 to date.

There has already been a significan­t amount of money invested into the design. If the scope/design changes then there is a risk that this investment is wasted.

Costs for further consultati­on covering the preparatio­n of documentat­ion, management of the process and assessment of feedback could be in the order of $100,000.

There will also be the need to consult through the LTP (2018-18) process. This will add up to an estimated two years onto the timeframes, which will flow through into increased constructi­on costs.

Additional procuremen­t costs for a combined design/build approach could be in order of $50,000-$100,000.

While awaiting decisions, costs are required to keep the existing facility operationa­l.

There is a need to consider whole of life costs when developing facilities. While an option may have lower constructi­on costs, it can often result in higher operation and maintenanc­e costs over the facilities’ life, resulting in a more expensive overall option. ‘‘The robustness of financial informatio­n is critical. Whatever option is chosen, there is the need for good financial/cost informatio­n that council can rely upon and which is not subject to a lot of assumption­s and therefore open to variations.

‘‘The financial/cost informatio­n should be at a comparable level to that which the work to date has been based upon.’’

Should the council not proceed with the refurbishm­ent project the council would need clear, documented rationale as to why it had not proceeded as per consultati­on previously, the report says.

‘‘There will be the need to reconsult with a similar quality of informatio­n and level of rigour. As mentioned previously, the 17-year length of this project is unusual and there would be a high level of community expectatio­n that the project should proceed on the basis that it has been consulted upon to date.’’

At the board workshop, it was raised an incorporat­ed society or trust be formed to deliver the project.

‘‘The use of an incorporat­ed society/trust to deliver projects of this nature has been used elsewhere by local government. Some of these have been successful but others have failed.’’

Before a decision could be made, detailed considerat­ion should be given to the pros and cons.

‘‘The key issue raised previously around the need to undertake appropriat­e analysis and consultati­on is still relevant and council would need to be very clear on the reasons and benefits for using an incorporat­ed society/ trust to deliver the project rather than council.’’

The report also noted during previous community engagement, a petition with 754 signatures, out of 4143 Cromwell residents, was presented requesting that council proceed with the refurbishm­ent project.

 ?? EMMA DAWE/STUFF ?? The Cromwell Memorial Hall.
EMMA DAWE/STUFF The Cromwell Memorial Hall.

Newspapers in English

Newspapers from New Zealand