Waikato Herald

Library closed

Concern at earthquake risk factor

- Danielle Nicholson danielle.nicholson@nzme.co.nz

Hamilton's central library was closed on Tuesday morning amid concerns over its seismic strengthen­ing.

Hamilton City Council decided to close the library after it received a detailed seismic assessment of the building in the last few days that revealed a part of the building is only at 15 per cent of new build standard (NBS) and requires remedial work.

While other areas of the building rated higher— some as high as 100 per cent— the 15 per cent rating brings the whole building's rating down to 15 per cent overall.

Council has been provided with an indication of a repair method for the building, which involves installing carbon-fibre strips to connect the 15 per cent part to the rest of the structure.

Council's general manager community Lance Vervoort said the work was expected to costs hundreds of thousands of dollars and was unbudgeted.

It was not known how long the building, which was built in 1973, would be closed for but council emphasised the closure was “temporary and precaution­ary”.

Vervoort said council with have to go through a planning process first and consider options from engineers. It would then need to get consent for the remedial work.

The area of concern is on the top of the third floor which primarily houses heritage material, back-of-house staff and functional areas such as a kitchenett­e. It sits above public areas on the second floor of the building.

Vervoort said the “building is not unsafe but it could be in a seismic event”.

“That's where the risk is. If the floor went [in an seismic event] it could cascade through and cause a catastroph­ic outcome on floors below it.”

More than 40 library staff are affected by the closure. Some of them have been reassigned to suburban libraries while others will be shifted to the Municipal Building.

Just over 279,000 customers went through the Central Library in the 2015/2016 financial year— an average of 5365 each week.

A pop-up library will open in about two weeks in council's reception lounge on the ground floor of the Municipal Building.

In October Hamilton News sought details about council's facilities maintenanc­e plans and seismic and structural soundness for more than a dozen councilown­ed buildings and assets.

However, council's privacy advisor declined to release the informatio­n under the Local Government Official Informatio­n and Meetings Act.

“It is intended that a report be presented to council at its public meeting in February 2017, outlining facilities maintenanc­e and management of council's physical assets. As this report is expected to cover the informatio­n that would be incorporat­ed into a response to your questions the informatio­n is being withheld at this time as the informatio­n requested is, or will soon be, publicly available,” it said.

The newspaper has since laid a complaint with the Office of the Ombudsman about council not providing the requested informatio­n and the Ombudsman has confirmed it will investigat­e the non-disclosure.

Vervoort said at amedia briefing about the library's closure that the seismic assessment on the library had been commission­ed “a few months back”.

Following the Kaikoura earthquake on November 14, which was felt widely throughout

the region, Hamilton News asked if council had any of its buildings inspected by engineers for damage.

“All the council’s facilities were inspected on Monday morning by the asset managers at each of the facilities,” Vervoort said. “There was nothing found that would require any of these buildings to be closed. If there had been any significan­t damage found, we would have closed the building straight away for the safety of staff and the community.”

Council closed Founders Theatre in March after it was found that the theatre’s flying system posed a health and safety risk. A subsequent seismic testing report showed the building’s weakest point rates just 15 per cent to earthquake specificat­ion as well.

The flying system, installed in 1962, holds things like production lights, drapes, scenery, and stage effects above the stage using ropes, pulleys and weights. It also holds the fire safety curtain.

An independen­t health and safety report assessed there was a likely risk of the flying system failing at some point in time. It cannot be easily fixed or replaced without requiring other major work to the 54-year-old theatre.

At the time, council CEO Richard Briggs said while the closure was sudden it was wellknown Founders Theatre needed major work. Work had been done on the flying system in 2010 and 2014 to extend its life.

Fairfax reported in February 2015 that former mayor Julie Hardaker had raised concerns with staff that crucial maintenanc­e was required to ensure the facility remained open.

“We’re here today talking about catch up because that’s what this is, catch up,” Hardaker said at the time.

“We’re at the cliff face now and in a couple of years’ time, we are falling over it.”

It had been flagged back in in 2015 that the theatre’s fly tower and stage structure needed urgent work to avoid closure.

Hardaker said the fly tower’s lack of attention meant the asset had become dilapidate­d.

“If they had accurate asset management plans since then, I guess we wouldn’t be having this discussion because it would have been dealt with long ago.”

 ??  ?? Hamilton central library was closed this week after a detailed seismic assessment revealed the building is at only 15 per cent of new build standard.
Hamilton central library was closed this week after a detailed seismic assessment revealed the building is at only 15 per cent of new build standard.
 ?? Photo / FILE ?? Hamilton City Council chief executive Richard Briggs (left) and general manager community Lance Vervoort.
Photo / FILE Hamilton City Council chief executive Richard Briggs (left) and general manager community Lance Vervoort.

Newspapers in English

Newspapers from New Zealand