Transport centre on target for October completion

-

Constructi­on on the new Rotokauri Transport Hub in Hamilton is back on track and scheduled to be completed at the end of October after work was halted in March due to Covid-19.

The October completion date of the transport hub supports the proposed November launch date of the new Hamilton to Auckland passenger rail service.

The new hub, which will include a park and ride, rail station, bus interchang­e and pedestrian connection to The Base, will also be a main interchang­e for the new Hamilton to Auckland passenger rail service.

Work on the Rotokauri station was shut down when the country moved to alert level 4, resulting in constructi­on delays. When the Government eased restrictio­ns at alert level 3 constructi­on started up again on the transport hub and the new October finish date confirmed.

Councillor Ewan Wilson, Hamilton City Council’s representa­tive on the rail governance working group, said restarting the project, and initiating the start-up passenger rail service, is an important step in supporting the local and regional economy.

“The council and its contractor­s have done everything possible to maintain momentum on key projects in recent months. This new service isn’t just about safer transport options, it’s also about offering social and business connection­s and another boost to domestic tourism which will play a huge part in our country’s economic recovery postCovid-19,” Mr Wilson said.

The council’s developmen­t general manager, Chris Allen, said there’s no getting around the impact the Covid-19 shutdown has had on the project, but the team have worked closely with the contractor to establish this revised completion date.

“Given the current climate and the health and safety guidelines in place on site good progress has been made these last couple weeks on the rail platform, roading upgrades, passenger bridge and stairs,” Mr Allen said.

Hamilton City Council is building the new transport hub at Rotokauri and upgrading the Frankton station with funding support from Waka Kotahi NZ Transport Agency.

The Waikato Regional Council is operating the service, working alongside Hamilton City Council, KiwiRail, Waka Kotahi NZ Transport Agency, Waikato District Council and Auckland Transport.

The transport hub project includes:

■ A new rail platform to initially provide for two return train services a day to the Papakura train station in Auckland, where connection­s could be made to the wider rail network.

■ A bus interchang­e including bus bays and a platform.

■ A park and ride facility which will provide car parking for rail and bus passengers, including mobility parking, electric vehicle parks, designated drop-off/pick-up zones and a taxi stand.

■ A over-rail pedestrian bridge to safely connect the Hub and The Base — creating a safe way to get to the station across the rail.

■ New and improved walking and cycling connection­s along most of Tasman Rd and along a new road (not yet named).

■ Changes to how people can drive, walk and cycle along Tasman Rd.

 ?? Photo / Supplied ?? The Rotokauri Transport centre is taking shape with a completion date of October.
Photo / Supplied The Rotokauri Transport centre is taking shape with a completion date of October.
 ?? Photo / Waikato Regional Council ?? An interior view of one of the new carriages to be used on the Hamilton to Auckland commuter rail service.