Weekend Herald

$13m Queen St cost ‘ridiculous for bit of paving’

Mayor and civic figures criticise price tag and lack of transparen­cy

- Tom Dillane

The final price tag for Auckland’s controvers­ial Queen St pedestrian­isation project — which launched a High Court challenge in 2021 by aggrieved landlords — has come in at $12.8 million, with the mayor and other civic figures claiming its costing and delivery “wasn’t really transparen­t”.

Auckland Council originally priced a Queen St “makeover” project at $1.1m in early 2021, after significan­t backlash over plastic Covid social distancing barriers that reduced the city’s main shopping thoroughfa­re to one lane.

More than three years after the initial effort to pedestrian­ise the street, the final component of the project is still being constructe­d, replacing wooden planking with stone pavers and upgraded planters between Shortland and Customs Streets.

On his election a year ago, Auckland mayor Wayne Brown outlined an agenda to reform Auckland Transport (AT), saying “they are there to serve the way we live, not change the way we live”.

Brown told the Weekend Herald this week he was not particular­ly familiar with the origins of the Queen St project but “there are quite a few old legacy projects I wouldn’t [endorse] working their way through the system. I’m on top of the big-cost mistakes like City Rail Link.”

Auckland Central MP Chlo¨e Swarbrick was a supporter of Auckland Council’s Access for Everyone project, which the pedestrian­isation of Queen St was part of. But she expressed some frustratio­n around the prioritisa­tion of the council’s city centre funding.

“The CRL is about to open in a few years, so now really is the time to do this stuff. But we could do a lot more with what we have without having to do massive infrastruc­ture projects,” Swarbrick said.

“There’s just so many more things council could be doing in vibrancy and actually unlocking the talent and opportunit­y that we already have here, but it seems to be focused solely on these infrastruc­ture projects and doing these consultati­on carousels.”

Swarbrick said there were simpler options, such as ease of access to street food licences, that could massively enhance the city centre.

But she found it “incredibly frustratin­g” that New Zealand tends to take a “peculiar exceptiona­list stance that all of these things that have worked in all these other jurisdicti­ons” such as a pedestrian-friendly city centre “for some reason aren’t going to work here”.

Viv Beck, chief executive of Auckland central business associatio­n Heart of the City, was part of a group of disgruntle­d businesses and property owners who filed an unpreceden­ted High Court action against the project in April 2021.

As the project is now nearing completion, Beck has reflected on how the street functions.

“On the positive side, people do seem to like having extra public space and they find the ease of walking around good.”

But Beck reiterated a longstandi­ng frustratio­n about the decision to not allow cars to access the section of Queen St outside Aotea Centre and the Civic.

“We are supportive of public transport, but it’s just that ongoing sort of commentary from AT, you know, the arts precinct at night should be an accessible place for everyone,” Beck said. “The lack of willingnes­s over a long period of time to talk about how that can be improved.

She said she still heard comments from physiother­apists with offices on Queen St about the difficulty of access for their injured patients. “I get comments from emergency services and cabs about [how] access is difficult.”

Beck was also critical of the communicat­ion from AT on how much the Queen St pedestrian­isation trial would cost and the more permanent constructi­on phase that has been drawn out for two years.

“Even those early works, we thought those, plastic [pylons] wouldn’t last — we actually told them that. But they went ahead anyway. So, you know, they’re digging it up now and making it like the rest of it.

“But the reality is, it wasn’t really transparen­t.”

Paradoxica­lly, AT’s decision to remove private vehicles taxis and rideshare vehicles from mid-Queen St, between the Civic Theatre and Aotea Square, was argued as a way of enhancing the city’s arts precinct.

“Pedestrian priority is key as this area is completed and re-invigorate­d post-Covid,” AT head of transport and parking compliance Rick Bidgood said.

“The city centre needs to enjoy good commerce, so commercial vehicles delivering goods are able to use this lane along with public transport and people travelling on two wheels.”

Fines are handed out to vehicles that drive through this section twice — with a pardon for a first infringeme­nt.

In September 2022, Bidgood said AT had issued 51,000 warning notices to cars that had used that section of the road.

Auckland Council head of city centre programmes Jenny Larking clarified to the Herald that the original price tag of $1.1m was only for the phase 1 trial changes that extended from Customs St to Shortland St, including Fort St, intended to be in place until at least September 2021.

The $12.8m figure relates to the full and completed project from Customs St through to Mayoral Drive and includes the original $1.1m.

“This project is a key part of the work by the council group and the business community to make the city centre more attractive and peoplefocu­sed,” Larking said.

“Footfall at the bottom of Queen St, on the east side — the site of the current works — through 2021 was 4.3 million people; in 2022 it had grown to 5.2 million and this year it is already at 5.4 million, with November and December — the two busiest months last year — still to come.”

Larking maintained the programme of works was within budget, with about two-thirds of the funding coming from targeted rates, and the remainder from general rates.

The group, the “Save Queen Street Society” was made up of 13 committee members including property owners and business figures who applied for an injunction to halt the works arguing it was unlawful and caused “significan­t economic harm”.

Property developer and Queen St landlord Andrew Krukziener spearheade­d the group, which eventually withdrew its High Court appeal for a judicial review after compromise­s to the extent of the streetscap­e alteration­s.

“It was a mistake then. It’s a mistake now,” Krukziener said.

“Everything they’ve done is totally unnecessar­y and has taken away the utility and ability for the street to be used intelligen­tly.

“I was in my car the other day and there was a bus driver with the window open and I said: I said, how long have you been a bus driver? He said 30 years. I said: ‘Mate, what do you think of what they’ve done to Queen St?’ He said ‘it’s the most stupid thing I’ve ever seen’. And it’s coming directly from the bus driver who this idiocy is supposed to have been making it better for.”

Krukziener said he believed the population level of Auckland and its spread-out geography meant the city would be dependent on cars for decades and it was a denial to think older people could rely exclusivel­y on cycling or buses.

He also said the original price tag of about $1m should have been more than enough to deliver the full permanent street changes.

He said the $13m price tag was “ridiculous” for “a bit of paving”.

“I fought against it, very, very hard and got some concession­s.

“But fundamenta­lly, you know, the council ended up doing 70 per cent of what they wanted to do and they should have got . . . zero per cent.”

 ?? ?? The final component of the Queen St project is still being constructe­d. Photo / Michael Craig
The final component of the Queen St project is still being constructe­d. Photo / Michael Craig

Newspapers in English

Newspapers from New Zealand