Weekend Herald

NZ must up power game — Transpower

More supply flexibilit­y required to meet demand peaks this winter

- Jamie Gray

National grid operator Transpower says New Zealand needs to up its investment in flexible power systems if it is to meet increased demand this winter.

The state-owned company has called for a step-change in investment in flexible power-system resources such as fast-starting generators, gridscale batteries and demand that can be reduced quickly when the power system is tight.

In its winter outlook, Transpower said the system needed more flexible resources to ensure sufficient electricit­y supply capacity to meet peak winter demand as New Zealand transition­ed to a more renewable and intermitte­nt electricit­y supply.

The company expected the winter to be challengin­g from both a peak and energy perspectiv­e, due to a combinatio­n of continued demand growth, increased intermitte­nt generation and its uncertaint­y during peak demand periods, the availabili­ty of firming generation due to planned and unplanned outages, project delays for the Tauhara geothermal and Harapaki wind farm projects and insufficie­nt fast-start capacity.

Transpower’s general manager operations, John Clarke, said until more flexible resources are added to the system the industry would need to continue to work particular­ly hard together to ensure a reliable electricit­y supply for Kiwis.

As grid operator, Transpower issued 14 customer advice notices (Cans) — a “heads up” to power generators when residual power to the grid is expected to drop below 200 megawatts — last year. That was up from 13 in 2022 and 10 in 2021.

“As New Zealand transition­s towards more renewable generation, thermal generation is needed on the coldest mornings and evenings to provide security of supply when wind generation drops or if faults happen on the system,” Clarke said.

“However, much of New Zealand’s thermal generation fleet is slow-start and not suited to this firming role, unless it is already running.

“This poses a real co-ordination challenge for the industry to make sure all available generation is turned on and ready to be dispatched when demand is at its highest. Additional flexible resources will make a real difference.”

Genesis Energy and Contact Energy are relied on to supply thermal backup when the system is under pressure.

Clarke said the industry had responded well to the winter peak capacity challenge the past two winters,

This included unplanned outages to about 700 megawatts of generation capacity last year due to several longterm unplanned outages of major generation units.

This was about 10 per cent of peak demand during the coldest mornings and evenings.

The outages contribute­d to eight low residual generation situations last winter, four of which would have escalated to grid emergencie­s without industry responding through a mix of delayed or cancelled outages of other generation units and the commitment of additional slow-start thermal units.

Clarke said grid emergencie­s typically required Transpower to work with local lines companies to manage demand.

This would initially mean turning off hot water cylinders for a short time but could include power cuts if the electricit­y supply shortfall was significan­t.

“Thanks to co-operation from industry to make sure all available capacity was offered when needed last year, we were able to get through a really tight winter without any disruption to consumers’ electricit­y supply,” Clarke said.

“But we have been saying for some time that we need more flexible resources in the system and we urge industry to accelerate the necessary investment­s.

“This is particular­ly the case at this stage of New Zealand’s transition to increasing amounts of intermitte­nt renewable generation in the system.”

Demand response also has a key role to play in the power system both now and into the future, Clarke said.

Five new electricit­y generation resources began offering electricit­y to the wholesale electricit­y market last year, the most in a single year since the current market was establishe­d in 1996.

Collective­ly, the new units can offer 378 MW of electricit­y under ideal conditions, or about 4 per cent of New Zealand’s almost 10,000 MW of total installed generation capacity.

Two major milestones

The new resources included three wind farms plus two significan­t milestones for the New Zealand electricit­y industry — the first utility-scale solar farm and the first utility-scale battery energy storage system, Wel Networks’ 33 MW Rotohiko battery.

The new renewable intermitte­nt generation connected to the market last year would provide much-needed energy across winter, Clarke said.

“But with peak demand growing year-on-year, increased investment in flexible resources like the Rotohiko battery will be critical to ensure we have the capacity to meet peak demand when the sun is not shining and the wind is not blowing.”

Late last year, Genesis Energy’s new chief executive, Malcolm Johns, previously chief executive of Christchur­ch Airport, said the level of risk inherent in New Zealand’s electricit­y system would not be tolerated in the aviation world.

“System risk, as managed in electricit­y, is very different to aviation, and aviation would not tolerate the system risk that is sitting in electricit­y at the moment,” Johns told the Herald in November.

Mercury and Meridian Energy, which have extensive renewable generating assets, have called for more thermal peaking capacity to be built.

As it stands, gas backs up the electricit­y grid, mostly through Genesis Energy’s coal- and gas-fired Huntly power station and Contact Energy’s fast-start “peaker” plants in Taranaki.

Genesis’ gas-fired turbine — Unit 5 — at Huntly was out of action for several months last year after one of its three circuit breakers failed. Unit 5 returned to service in late January.

In September, Contact announced the failure of one of its gas-fired, faststart peaking units — GT22 — which supplies power to the grid when the system is stressed.

In an update provided to the Herald, Contact said it worked hard with GE to accelerate the repair and return of the unit to New Zealand.

The unit is now expected to arrive in May — ahead of the original March 2025 date.

“This would be an improvemen­t to what Transpower have modelled,” Contact said.

“This important unit should assist in improving winter security margins and we are pleased to see it will be available for 2024 winter,” the company said.

Contact also said it expects to run its gas-powered Taranaki Combined Cycle plant through this winter.

 ?? Delhi. Photo / Getty Images ?? The Rashtrapat­i Bhavan is the official residence of the President of India located at the Western end of Rajpath in New
Delhi. Photo / Getty Images The Rashtrapat­i Bhavan is the official residence of the President of India located at the Western end of Rajpath in New

Newspapers in English

Newspapers from New Zealand