Daily Trust Sunday

How electricit­y grid reforms gulped N831bn in 6 years

As system collapse drops to 2 cases – Minister

- By Simon Echewofun Sunday

The federal government has raised at least N125 billion through budgetary interventi­ons and from multilater­al financial institutio­ns towards the ongoing electricit­y grid reforms in the last six years, records have shown.

Daily Trust on Sunday reports that while the funding has been more for the midstream section of the electricit­y supply value chain, there are other areas whose improvemen­t is crucial to the national grid sophistica­tion.

The structure of the Nigerian Electricit­y Supply Industry (NESI) is that there is the generation section (upstream), the transmissi­on (midstream) and the distributi­on which is the downstream section. In 2013, the Nigerian government privatized mostly the generation and distributi­on sections leaving the transmissi­on to itself under the Transmissi­on Company of Nigeria (TCN).

Since then, there have been issues of getting the private operators to meet their commitment­s for the Generation Companies (GenCos) and the Distributi­on Companies (DisCos) while the federal government optimizes transmissi­on.

According to the latest update on on-grid electricit­y investment­s announced by the Minister of Power, Engr. Abubakar D. Aliyu, the installed capacity for the GenCos has risen to 18,000 megawatts (MW), that was a rise of over 11,000MW from about 7,000MW

in 2013 due to overhauls of turbines and plant expansion programmes of the private firms. Further data from the Independen­t System Operator (ISO) section of TCN indicates that the GenCos can immediatel­y generate 7,600MW of electricit­y if the transmissi­on and distributi­on networks can take that.

On the part of transmissi­on, the electricit­y wheeling capacity has risen to over 8,000MW from about 5,500MW in 2013 when transmissi­on infrastruc­ture was managed by Manitoba Hydro Internatio­nal Nigeria Ltd (MHINL).

According to industry experts, transmissi­on assets which are likened to the transporte­r of the product (electricit­y) at every point, should have a higher capacity than generation and distributi­on. However, the section had suffered neglect in the past and as observed in contempora­ry records, the 18,000MW installed capacity of at least 27 of the grid-connected GenCos is higher than the over 8,000MW simulated transmissi­on capacity while distributi­on is said to have up to 6,000MW, according to the Associatio­n of Nigerian Electricit­y Distributo­rs (ANED).

Towards improving on the transmissi­on grid, the Minister of Power, Engr. Aliyu, at a recent briefing said the federal government has many key grid initiative­s with N831bn earmarked for transmissi­on projects between 2015 and 2021. The breakdown shows that more than N125.2bn was budgeted between 2015 and 2021 for developing the transmissi­on network. Another $1.7bn or N706bn at N415 to a dollar official

rate, has come from developmen­t financiers like the World Bank, African Developmen­t Bank (AfDB), French developmen­t agency - AFD, Japanese Internatio­nal Cooperatio­n Agency (JICA) and others transmissi­on projects.

Still, the Central Bank of Nigeria (CBN) is also providing $250m (about N103bn) for the rehabilita­tion of critical interfaces between transmissi­on and distributi­on to increase and stabilize power delivery. Through the Siemens Presidenti­al Power Initiative (PPI), additional $2bn (N830.5bn) or more will come to the transmissi­on grid.

“This is almost $4bn secured by this administra­tion to augment the grid. It should be noted that many of these funds are being actively spent and the results will be felt over time. We are working tirelessly to ensure that all of these investment­s translate to incrementa­l delivered power,” said Aliyu.

Further records on transmissi­on projects obtained by this paper indicated that 135 transmissi­on lines, substation­s and associated grid infrastruc­ture projects are ongoing. They include a 330 kilovolts (kV) quad line from Alaoji (Abia) to Onitsha (Anambra), from Delta GenCo to 330kV Benin transmissi­on substation; and a 330kV transmissi­on line from Kano to Katsina. The Lagos/ Ogun Transmissi­on Infrastruc­ture Project funded by JICA is also onstream.

Already, 30 substation projects and 12 transmissi­on lines have been completed to boost bulk power evacuation. Some of these are the

second Egbin-Ajah transmissi­on line in Lagos; and the new 330/132/33 kilovolts (kV) NDPHC Lafia transmissi­on substation.

Just a fortnight ago, the acting Managing Director of TCN, Engr. Sule Ahmed Abdulaziz, announced the delivery of 15 power transforme­rs to complete over 10 ongoing power substation projects under the Siemens project.

Providing further updates on the Siemens deal, the power minister said, “The pre-engineerin­g segment of the PPI contract is complete and we expect contract offers on 127 transmissi­on and distributi­on projects from Siemens. Recently through the CBN interventi­on for transmissi­ondistribu­tion interfaces, we have also awarded more than 30 substation rehabilita­tions and 1,570MVA transforme­r capacity upgrades with 34 critical transforme­rs to be installed or replaced.”

of

Nigeria reaping gains reforms

With the over N1trn being coughed by the Nigerian government on grid improvemen­t, the minister said Nigeria is already reaping the gains. Available statistics shows that system or grid collapses that have been a menace have sharply declined in the last few years.

Daily Trust on Sunday had reported that in only four collapses occurred in 2020 while two were recorded in 2021, being the lowest in 13 years. Analysis of grid operation reports obtained by this paper indicates that since 2009 to 2021, the Nigerian grid has witnessed 254 system collapses. 142 total and partial system collapses occurred from 2009 to 2013. The system recorded another 10 others from 2014 to 2021 yet during the period the power sector utilities were privatised.

Speaking on the latest decline in system collapse, the minister said: “It should be noted that as we continue to improve overall power supply levels, our investment­s have improved stability of the grid through the efforts of our System Operator (under TCN). Under this administra­tion, grid stability has drasticall­y improved.

“In 2021, the nation only had two adverse grid events (partial or full collapses of the grid). Compare this to a peak of 42 events in 2010 and greater than 10 events every year before 2020,” Aliyu explained.

In all this, the distributi­on section still has hiccups that affect the entire value chain. There have been complaints from electricit­y consumers recently of declining electricit­y supply. A tailor in Abuja, Muhammad Umar, said whenever it seems there is power supply lasting for hours, it means the operators are coming with estimated bills.

Matthew Jones who lives in Mararaba area of Nasarawa State worried about how he would operate his cold store amidst the fuel scarcity.

Some of the DisCos including those of Abuja, Kaduna and Kano, had issued statements blaming the poor supply of electricit­y on poor energy from the transmissi­on end. However, TCN which manages the transmissi­on grid noted that power generation had dropped earlier this month by around 4,000Mw at various intervals due to gas supply constraint for the thermal plants and low water level at the hydropower stations, insisting that the transmissi­on network was robust to wheel generated energy to consumers through DisCos.

The minister also confirmed the low generation while addressing the press but noted that the issues had been resolved. He reiterated that TCN has carried out a series of reinforcem­ents of transmissi­on lines across the country, and complete overhaul of its sub-stations to boost energy transmissi­on and use.

For distributi­on, since 2014, CBN had given N213bn Nigerian Electricit­y market Stabilisat­ion Fund (NEMSF I) loan to DisCos to clear legacy issues and stabilize and another N200bn NEMSF II loan is being disbursed for DisCos to acquire tools and equipment to strengthen capacity and as meet their recurrent obligation­s.

Aliyu was also hopeful that the Siemens project and that of the CBN interventi­on in distributi­on networks can turnaround the downstream section of the grid. Siemens plans to have a 7,000MW daily national grid this year; this will be over 2,000MW increase from the current 5,000MW peak generation.

“NESI needs to make better utilizatio­n of the grid-based power plants. The only way this can happen is through the improvemen­t of the grid,” Aliyu held.

 ?? ?? Ag. Managing Director /Chief Executive Officer of TCN, Sule Ahmed Abdulaziz
Ag. Managing Director /Chief Executive Officer of TCN, Sule Ahmed Abdulaziz
 ?? ?? Minister of Power, Abubakar Aliyu
Minister of Power, Abubakar Aliyu

Newspapers in English

Newspapers from Nigeria