Daily Trust

Electricit­y generation dips by 774mw, drops to 3,292mw in 24hrs

- By Simon Echewofun Sunday

Electricit­y generation yesterday dropped by 774 megawatts (mw) barely 24 hours after it reached a peak of 4,066mw, national statistics from the Independen­t System Operator (ISO), a public firm has shown.

The grid recorded tremendous improvemen­t on Sunday after 78,573 megawatts hours (mwh) was wheeled out for distributi­on to an estimated six million customers by 11 Distributi­on Companies (DisCos).

It, however fell to 2,876mw during the offpeak period, recording a difference of 1,190mw. This is a time of the day when industry experts feel demand from customers reduced and as such, power plants often ramped down their generation level.

By yesterday, during the period of estimated highest demand of electricit­y often called ‘peak period’, generation level however went down to 3,292mw signifying adequate power supply for the vast customers in the fresh working day.

Further statistics from the National Control Centre (NCC), Osogbo where ISO controls the nation’s power pool revealed that this month, August, began with high generation of 4,282mw with a capability to reach 4,878mw as at Wednesday August 2, 2017.

However, the trailing constraint­s of load unutilisat­ion caused by DisCos’ load demand (load rejection), inadequate gas supply and transmissi­on frequency affected sustenance of the positive trend. Sadly, power fell to a pitiable 2,833mw the same day.

Customers denied 2,133mw as load rejection, gas shortage trend

In the midst of the power inadequacy in Nigeria, a huge level of electricit­y has continued to be unutilised in the national grid and many of the estimated six million electricit­y users deprived of sustained power supply. The grid data provided for last Thursday showed that 2,133mw was lost to these monstrous issues.

The major disappoint­ment to the national grid and to electricit­y customers last Thursday was with the 11 Distributi­on Companies (DisCos) when 1,253mw was lost to their varied load demand constraint­s resulting in constraint­s managing the frequency of transmissi­on network.

Nine power stations were affected by this with 15 of their turbines forced to become idle. From the analysis, the biggest losers were two turbines in Afam VI that lost 283mw.

Sustained gas supply to the thermal stations has been a major challenge. This cut down 505mw electricit­y supply in four turbines across four power stations under the National Integrated Power Projects (NIPP). Their capacity record showed that Geregu NIPP could generate 145mw. Alaoji’s two turbines would have produced 240mw and a turbine in Omotosho would have fetched the grid another 120mw.

There was also a challenge with the transmissi­on lines which caused the loss of 375mw, shutting out eight turbines in five power stations. While a turbine in Omoku station lost 115mw, Omotosho Gas lost 114mw from three turbines, and Olorunsogo Gas lost 76mw from two turbines. A turbine in Olorunsogo NIPP lost 38mw, and another in Omotosho NIPP lost 32mw.

Three hydropower plants constraine­d in rainy season

Daily Trust analysed the generation level of the three hydropower stations which was expected to be high during the rainy season. Data revealed that the expectatio­ns are being cut short due to certain technical constraint­s. Kainji hydro which has installed capacity of 440mw produced 232mw last Wednesday. 208mw was constraine­d because four of its units have technical issues caused by battery loss, high temperatur­e and fire.

Jebba Hydro has 386mw capacity but generated 251mw. 135mw was lost as three of its units have frequency maintenanc­e issues. Shiroro hydro has 600mw capacity being the largest of the hydro plants but it produced just half of its capacity as 300mw was lost.

 ??  ??
 ??  ?? Electricit­y pylon
Electricit­y pylon

Newspapers in English

Newspapers from Nigeria