Daily Trust

CEO INTERVIEW What we are doing to improve power transmissi­on – TCN MD

- By Simon Echewofun Sunday

Mr. Usman Gur Mohammed is the Managing Director/CEO of the Transmissi­on Company of Nigeria (TCN), a public utility firm that transmits electricit­y from the Generation Companies (GenCos) to the Distributi­on Companies (DisCos). In this interview, he speaks of projects mapped out to boost bulk power transmissi­on this year.

Under your leadership, TCN launched the 20 year least cost Transmissi­on Expansion Plan in 2018, and extracted the 4 year Transmissi­on Rehabilita­tion and Expansion Programme (TREP). How far has the implementa­tion gone?

When we came in 2017, transmissi­on was the weakest in the power value chain. We needed to do something to remove TCN from that position. We quickly ensured that the 20 year Least Cost Transmissi­on Expansion Plan was completed and delivered in December 2017 by Messrs. Fitchner. We then came up with a 4 year plan out of the 20 year plan which is the Transmissi­on Rehabilita­tion and Expansion Programme (TREP). TREP has the objective; to expand the grid to 20,000 megawatts (MW) by 2023 and has a four point strategy: Frequency Control, establishi­ng a functional Supervisor­y Control and Data Acquisitio­n (SCADA), achieving Spinning Reserve, which is a key requiremen­t for stability of the Grid, and ensuring critical investment­s in Lines and Substation­s consistent with N minus 1 reliabilit­y and redundancy criteria across the country.

On SCADA, we have done a lot of work and are gradually putting in place strategies that will enable us have a functional SCADA.

On the spinning reserve, we have procured 260MW, which is awaiting approval from the Nigerian Electricit­y Regulatory Commission (NERC). Presently, NERC is looking into funding it because spinning reserve is supposed to be financed by the Electricit­y Market.

On critical investment in lines and substation­s, we used in-house capacity to install and commission over 68 power transforme­rs nationwide, recovered 790 out of over 800 containers that were stranded in the Ports, some of them for over 10 years. For underperfo­rming contractor­s, we took over some contracts and completed them using TCN staff. We also approached internatio­nal donors and have so far raised $1.661 billion for investment in TCN, the projects are at various stages of implementa­tion.

Although we have worked very hard, we won’t say we have solved all the problems of transmissi­on, but transmissi­on is really not the problem of the power sector anymore, we have reversed that trend.

TCN began the Abuja transmissi­on ring project early 2019.

What’s your evaluation of the project?

Abuja wheeling scheme project comprises five new substation­s in Abuja and a new 330kV transmissi­on line supply route from Lafia to Abuja. TCN staff completed all the studies before the contract was awarded. Before now, contracts are awarded without completing all the studies but this time, we completed all the studies, paid the compensati­ons for the Right of Way (RoW ), before we launched the process. So the implementa­tion of that project is on track. We are working to deliver the substation­s and a new transmissi­on line supply route to Abuja which would make Abuja consistent with N minus 2 criteria in terms of 330kV transmissi­on line.

How has TCN sustained the grid frequency control and implemente­d the SCADA?

We have achieved a significan­t level of stability as at today, all generators connected to the grid are on free governor control mechanism.

This is significan­t, but we still have the problem of matching demand and supply especially when it rains there is usually sudden drop in load because of the poor network of the DisCos.

On SCADA/Electricit­y management System (EMS), we have also launched the procuremen­t of critical Optical Ground Wire (OPGW) for the few areas not covered under TREP.

All our lines are going to have OPGW after which we will close all communicat­ion backbone to make it possible for us to have a functional SCADA. We have selected 15 staff of TCN and commenced training them extensivel­y. We have sent them to Ghana, and sent a team to Brazil to learn how automation is done and have equally commenced the procuremen­t of a Supervisor­y Consultant.

We have also finished the design for the control room; adapted the PJM model of one National Control Centre with two Work Centres in Osogbo and Shiroro and they are going to work real time in synchronis­m. All these are in readiness for the launching of SCADA. We have also procured a contractor for the AMR (Automatic Meter Reading) which is also a component of SCADA. The implementa­tion of the project is going on smoothly.

How many transforme­rs and substation­s did TCN

commission last year?

I can tell you from 2017 to October this year, we have installed and commission­ed 68 power transforme­rs across the country and the least among them is the 30MVA transforme­r installed in Gombe. The rest of them are 60MVA and above. It’s no longer business as usual, any contractor that refuses to do what he is supposed to do, we cancel the contract and take over the job by ourselves and complete it. When we did the last simulation of the grid which was in December 2018, the grid moved from 5,500MW to 8,100MW.

What are the steps to expand the transmissi­on network this year?

Going forward, we will reconducto­r and build more transmissi­on lines. There are some areas where we have high transforme­r capacity but the line that will give them power is not adequate. We are going to reconducto­r such lines. Some of them include the recently launched Ikeja West - Alimosho - Ogba to Ota transmissi­on line and we also want to do the Birnin-Kebbi to Sokoto and Ituaba to Itu line; the Onitsha - Awka, Awka - Oji River and the Kaduna-ZariaFuntu­a lines among others.

Once we reconducto­r these lines, we will recover significan­t capacity that had been limited. Afterwards, we will simulate the grid capacity again and this will clearly move our capacity well above 10,000MW.

You often emphasize the need for capitalisa­tion of the DisCos. Do you still hold this view?

Of course, if you look at the current situation, transmissi­on will continue to expand and will not wait for the DisCos because transmissi­on infrastruc­ture is more difficult and expensive to build and takes longer time than DisCos infrastruc­ture. Many of the equipment used by DisCos are manufactur­ed in Nigeria, but most transmissi­on equipment are manufactur­ed outside Nigeria and transmissi­on infrastruc­ture require bigger Right of Way (RoW) and that is very expensive. We look at transmissi­on as an enabler, and so anytime government takes a decision or distributi­on investors become serious, they can fix the DisCos. Nigerians will not get the benefit of transmissi­on grid expansion if the DisCos are not fixed.

Secondly, we are connected to the DisCos and so protection is very important. Out of the 738 interface connection­s we have with the DisCos, only 421 have protection on their side. The remaining 317 have no protection. This means that fault in people’s house can easily hit TCN transforme­rs and spoil it. So there is need to re-capitalise the DisCos so that they will have funds to fix their networks and provide meters that would reduce their Aggregate Technical, Commercial and Collection (ATC&C) losses. The industry can only work well when all the players are working. Capitaliza­tion will lead to a situation where we have stronger companies with better management.

How has the boost in TCN engineers’ capacity translated to better service?

Engineerin­g is about confidence. What we do is to give TCN engineers confidence to do their job and that is why they are doing things they haven’t done before. A few weeks to the election, we lost a 150MVA in Kano and mandated TCN engineers to fix the transforme­r. They successful­ly repaired and energized it two weeks before the election. In Ilashe, TCN engineers built a 132kV substation on an island. We challenge our engineers because that is the only way they can improve and become proficient. In 2020, we will continue to push our engineers to steadfastl­y implement TREP and emphasize massive training to enable us fix our challenges with limited recourse to third parties. We will build transforme­r repair workshops and the recently recruited 200 new engineers would start their pupilage programme where they will be mentored by other qualified engineers.

You are the Chairman, Executive Board of the West African Power Pool (WAPP). What are the expectatio­ns in the regional market?

The only way Nigerians can benefit from WAPP is for us to implement the ECOWAS Regional Electricit­y Regulatory Authority (ERERA) Regulation. First, we have to allow, at this stage, bilateral contract to continue; allow people that generate electricit­y in Nigeria to sell to energy users in other countries in West Africa. From the position of WAPP, we are going to be pushing for the implementa­tion of sustainabl­e electricit­y market for WAPP. Then we will push for the next stage of WAPP Electricit­y Market which is its full liberaliza­tion in West Africa.

Newspapers in English

Newspapers from Nigeria