330 Kudendan-Mando transmissi­on lines at 80% completion – MD

- From Maryam AhmaduSuka, Kaduna

The managing director and chief executive officer of the Transmissi­on Company of Nigeria (TCN), Engineer Suleiman Abdulaziz, has said the 330 Kudendan to Mando transmissi­on line project is at 80 per cent completion.

The MD, while speaking at an inspection tour of the project in Kudendan and Mando in Kaduna, assured that they would meet the completion deadline of

December 2022.

Daily Trust reports that the project, which was awarded to Atlantic Engineerin­g Company in 2018, is expected to improve power stability in Kaduna and environs. Already, the contractor has successful­ly erected 38 towers out of 55.

According to the MD, “The Kudendan power station is generating 215 megawatts and we have to evacuate this power to Mando 330 sub-station in Kaduna. We are now building a 330 transmissi­on line from

Kudendan to Mando.

“In addition to that, we have the Gurara generation station which is generating 30 megawatts; that project has been completed a long time ago and the minister of Water Resources is always writing to the minister of Power to make sure that we finish our project so that the 30 megawatts can be evacuated.”

Highlighti­ng some reasons hindering the speedy completion of the project, the managing director said compensati­on is a major challenge.

He assured that talks are on with the Kaduna State government to find a solution to that saying, “Near the 330 substation in Mando, there is also land there and the owner is asking for compensati­on and according to TCN rules and regulation­s, we only pay for crops and property, we do not pay for land because the land belongs to the government.”

He then noted that TCN is also talking with the state government to find a way of resolving the issue.