The Guardian (Nigeria)

SNEPCO'S Bonga FPSO completes 2022 turnaround maintenanc­e

-

SHELL Nigeria Exploratio­n and Production Company Limited ( SNEPCO) has announced that the 2022 Turnaround Maintenanc­e ( TAM) of the Bonga floating production storage and offloading vessel ( FPSO) has been completed.

The 225kbopd capacity FPSO was shut down on October 18, 2022 to carry out statutory inspection­s, recertific­ations and other critical asset integrity restoratio­n activities.

The 2022 TAM, which was originally planned for 30 days, was completed in 22 days on November 9, 2022 as a result of front- end planning and flawless execution.

Commission­ing and startup activities are in progress and will culminate in ramp up of oil and gas production in the coming days.