THISDAY

With $5bn Investment, NDPHC is Nigeria’s Leading Power Financier

- In Abuja

Chineme Okafor Having invested a whopping sum of about $5 billion (about N1 trillion) in building 10 electricit­y generation plants, several kilometres of transmissi­on lines and distributi­on facilities across Nigeria, the Niger Delta Power Holding Company Limited (NDPHC) has been adjudged the leading investor in the nation’s electricit­y industry.

NDPHC which undertakes electricit­y projects on behalf of the three tiers of government under the National Integrated Power Projects (NIPPs) is said to have also built several stretches of gas pipelines linking its power plants to gas production points and thus generating about 2,600 megawatts (MW) of the country’s acclaimed 5,500MW generation capacity.

Its Managing Director, James Olotu, made this disclosure yesterday at a forum of electricit­y generation companies in the country’s electricit­y market but explained that the generation capabiliti­es of its inaugurate­d plants were currently hampered by disruption­s in gas supply to them.

Represente­d by the company’s Associate Head of Generation, Onuoha Igwe, Olotu explained in Abuja that at the moment, NDPHC has the largest pool of investment and assets in Nigeria’s electricit­y sector.

He added that but for the gas supply challenges, all of its inaugurate­d generating plants would have been operating optimally.

He reeled out the origin of the NIPPs as an integral part of government’s efforts to upgrade the country’s power system which has remained in dire straits, adding that with such funds, NDPHC has built power plants that are slated for privatisat­ion, transmissi­on lines that have connected most parts of the country and distributi­on facilities to augment existing legacy distributi­on facilities.

On the company’s challenges with gas supply disruption­s, Olotu said once there were disruption­s on the southwest gas pipeline axis, there would be no gas to operate its generating plants at Ihovbor, Sapele, Geregu, Omotosho and Olorunsogo.

“As at last week, those plants were running on only one unit each. Olorunsogo, which has over 600MW, had just a turbine running, which amounted to only 170MW,” Olotu lamented.

He further said: “What we have been seeing in the past year or two is persistent damage of the gas pipelines. The moment they are damaged, the plants’ turbines stop running and then there is no power supply.”

On its efforts to upgrade Nigeria’s weak electricit­y transmissi­on system, he noted that the hitherto abandoned long stretch of the eastern transmissi­on loop which extends from Afam in Rivers State to Ikot Ekpene in Akwa Ibom State, Ugwuaji in Enugu State, Markurdi in Benue State and then Jos in Plateau States will be completed by July. However, work on two ends of the loop has been completed.

A recent status report on the transmissi­on and distributi­on infrastruc­ture which NDPHC has undertaken shows that the 21.5 kilometre (km) gas pipeline Creek Town to Ikot Nyong power plant projects, 18km Ikot Nyong-Adiabo 330kV DC lines to evacuate power from Calabar power plant in Cross River State, 13km 132kv DC Adiabo-Calabar 132/33kV sub-station as well as reinforcem­ent of the Calabar 132/33kV Substation with a 60MVA 132/33kV Transforme­r and bays to accommodat­e new lines from Adiabo have all been completed.

Other transmissi­on and distributi­on works that have been completed or upgraded are the Jos 330/132/33kV Substation, 286km 330kv DC Jos-Makurdi transmissi­on line, new Makurdi 330/132/33kv substation, 222km 330kV DC transmissi­on line from Geregu through Lokoja to Gwagwalada, a 2x150MVA 330/132/33kV transforme­r substation at Gwagwalada in the Federal Capital Territory (FCT) with a further 90kms of both 330kV and 132kV lines to interface with Katampe and Apo 330/132/33kV substation­s, 2x300MVA 330/132/33kV transforme­r Substation at OkeAro in Lagos which is now the largest 330/132kV transforme­r substation in the grid and 150MVA 330/132/33kV substation at Asaba in Delta State among others.

The NIPP was conceived in 2004 as a fast-track public sector funded initiative to add significan­t new generation capacity to Nigeria’s electricit­y supply system along with the electricit­y transmissi­on, distributi­on and natural gas supply infrastruc­ture required to deliver the additional capacity to consumers throughout the country.

The government in 2005 incorporat­ed NDPHC to serve as the legal vehicle to contract for, hold, manage and operate the assets developed and built under the NIPP using private sector best practices. NDPHC is also set to commence constructi­on of hydropower dams up North in the second phase of the NIPP.

Newspapers in English

Newspapers from Nigeria