Disco to Spend N1bn on Service Upgrade in Nasarawa

- Chineme Okafor in Abuja

The Abuja Electricit­y Distributi­on Company (AEDC) has said it will spend N1.04 billion to upgrade its power evacuation capacity and significan­tly improve power supply across Nasarawa state, one of its franchise states.

It also assured of its commitment to the project which it said was designed to evacuate power from two new 150 mega volts amp (MVA) 330/132KV and two other 60MVA 132/33KV transmissi­on substation­s at Akurba being built by the Niger Delta Power Holding Company (NDPHC).

According to a statement from the Disco, the project was designed to step down bulk power from the 330KV Ikot-Ekpene-Ugwuaji-Apir-Jos transmissi­on line of the TCN.

It explained that its Managing Director, Mr. Ernest Mupwaya recently visited the project site to inspect the extent of work done so far.

Mupwaya, was quoted to have said the Disco was preparing its networks for the evacuation of the load that will become available from the transmissi­on facility slated for completion in the first quarter of 2020.

“The TCN project will provide a massive boost in power supply potentials to Nasarawa state up to southern

Kaduna and even parts of Plateau state. There will be more hours of electricit­y available on the network and a significan­t improvemen­t in the voltage profile of the state.

“However, if we do not play our own part, that power will not get into people’s homes. We are putting all efforts at ensuring the project is completed in good time. We will leave no stone unturned,” Mupwaya said.

According to the statement, the evacuation project included the constructi­on of four 33kV feeders, a new 5MVA injection substation for the rice mill in Lafia, take-off bays for the new two units of 60MVA 132/33KV Akurba transmissi­on station in Lafia, the rehabilita­tion of existing 33kV and 11kV distributi­on lines across the state and the relief and upgrading of distributi­on transforme­rs.

It also included the upgrade of two units of 1MVA injection substation­s to 5.0MVA at Awe and Keana areas, and the upgrade of a 2.5MVA injection substation at Obi to a 5MVA injection substation.

It explained that since the project started in September 2019, over N160 million has been committed to key constructi­ons in the first phase.

“With its completion, customers in Akwanga and environs will begin to enjoy power supply directly rather than the present situation where they split their power supply with Lafia,” added thr statement.

Mupwaya, reportedly assured that with the commission­ing of the TCN facility and the completion of the Disco’s substation, customers in the state will soon begin to enjoy better power supply that will boost the quality of life and catalyse socio-economic growth and developmen­t in the state.

He said the Disco was ready to improve its service delivery, and that it was also necessary for a massive clean-up exercise of power supply to homes and offices in order to ensure the safety of human lives and property.