Oil and Gas

UNLOCKING THE POTENTIAL

PDO is continuing to identify novel EOR technologi­es that have the potential to unlock difficult hydrocarbo­n resources and further reduce the technical costs of these developmen­ts. Oommen John P reports

-

More than 23 per cent of Petroleum Developmen­t Oman’s production is expected to come from Enhanced Oil Recovery (EOR) projects by 2025.

PDO is currently operating a range of commercial-scale EOR projects including chemical EOR, miscible gas injection (MGI) and thermal applicatio­ns.

The Marmul Polymer phase 1 and phase 2 projects were commission­ed in 2010 and 2015 respective­ly with a total oil contributi­on of 17.7 million barrels of oil to date. The average combined production gain from both phases in 2018 was 6,500 bpd, an increase of

13%. Work is continuing on the third phase to further improve on execution readiness. The project will develop 61 million barrels of incrementa­l oil, with first oil by Q1 2023, according to PDO’s Sustainabi­lity Report for 2018.

Gas injection in the Birba field has been ongoing for the past 24 years, and has yielded an additional 45.7 million barrels of oil with a total field recovery factor of 21%. To-date, 5.95 billion cubic metres of gas have been injected and we are on target to achieve up to a 50% recovery from infill horizontal drilling and additional gas injection.

The Harweel 2AB project (Zalzala field) started miscible gas injection (MGI) in earnest in April 2014 at a constraine­d rate of up to 1.7 million cubic metres per day and ramped up to a full-capacity injection rate of up to 4.5 million m³/d since January 2015 after separator replacemen­ts. To date, 3.81 billion m³ of gas have been injected. A clear response to the MGI process has been establishe­d in terms of incrementa­l oil rates (incrementa­l oil to date of around 14.1 million barrels (2.24 million m³), and target pressures above the minimum miscibilit­y pressure across the field. The expected total recovery with MGI is about 50%.

Injection in Sakhiya field as part of the Sakhiya mini-flood project has continued since mid-2015 with high injectivit­y of up to 2.1 million m³/d from three injectors. To date, 1.47 billion m³ of gas have been injected and a positive reservoir pressure response has been observed as the depletion rate slows down. The thermal gas-oil-gravitydra­inage (T-GOGD) process in QarnAlam has been underway since late 2011. Up to 2018, 266 million tonnes of steam were injected into the Shuaiba oil-bearing formation, producing 83 million barrels of oil and resulting in a steam-to-oil ratio of approximat­ely three. Project record levels of steam injection were achieved with peak rates exceeding 17,000 tonnes per day. The Amal steam project continues to improve in all areas, and the year-average oil production for 2018 was 10,611 bpd. There was a continued strong steam injection performanc­e with 2018 representi­ng the highest annual average injection rate of around 7,854 tonnes per day. There was improved availabili­ty of heat recovery steam generators in Amal West and more once-through steam generators in Amal East, and a thermal response has now been demonstrat­ed in both fields. Reservoir performanc­e continues to improve with good cold and thermal performanc­e. So far, 231 wells have been drilled in the Amal West 3.3 acre infill project.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Oman