OETC completes constructi­on work of Mirbat power station

- JOMAR MENDOZA @Jmobserver

Oman Electricit­y Transmissi­on Company (OETC), a member of Nama Group, announced the successful completion of the constructi­on works of the Mirbat power station with a voltage of

132/33 kv and the associated transmissi­on lines from the Ashur station to the Mirbat station at a cost of more than RO 11 million. The project consists of six bays of 132 kv GIS, two transforme­rs of 132 kv to 33 kv and each of them has a capacity of 63 MVA.

The project includes protection devices, communicat­ion and fire protection systems. Meanwhile, work is under way to upgrade the efficiency of Thamrait station with a voltage of 33/132 kv from two transforme­rs with a capacity of 2x30 MVA to 2x63 MVA.

The project included new building 33 KV GIS with dismantlin­g two transforme­rs of 30 MVA and replaced by two transforme­rs with capacity of 63 MVA. The project is already 96.26 per cent complete with a cost of RO 3.4 million.

Last month, OETC completed the constructi­on of a solar energy transmissi­on station in the Wilayat of Ibri. The solar energy transmissi­on station, a 220kv grid station with a constructi­on cost of about RO 7.5 million, is the first grid station connected to solar power plant in Ibri.

 ?? ??