Business World

GNPower Kauswagan ramps up developmen­t of Mindanao power plant

- By Victor V. Saulon Sub-Editor

GNPOWER KAUSWAGAN Ltd. Co. (GNPK) has stepped up the developmen­t of one of Mindanao’s biggest power plants and has sought regulatory approval to build a point-to-point transmissi­on line from the facility to the national grid.

In its applicatio­n with the Energy Regulatory Commission (ERC), GNPK said it is building a clean pulverized coal- fired power generation facility with four units, each with a capacity of

138 megawatts (MW) or a total of 552 MW.

GNPK, which is led by Ayala Corp. subsidiary AC Energy Holdings, Inc., is seeking ERC approval to develop, own and operate grid connection facilities with a capacity of 230 kilovolt ( kV) and a 69 kV.

“In order for GNPK to timely conduct the necessary testing and commission­ing of the first unit of the [ power plant] by the second half of 2018, GNPK intends to have the Dedicated Connection Facilities operationa­lly ready by then,” it said in its applicatio­n.

“GNPK and NGCP are currently discussing the terms and conditions of the connection agreement which will govern the interconne­ction and transmissi­on of power supply” from the generation facility into the Mindanao grid, it added.

The company is building the power plant in barangays Libertad and Tacub in the municipali­ty of Kauswagan in Lanao del Norte province.

In its applicatio­n with the ERC, GNPK said the power plant will be connected to the Mindanao grid through the Balo-I-Kauswagan-Aurora 230-

kV transmissi­on line. Given the location of the facility, its optimum connection to the grid network should be through the National Grid Corporatio­n of the Philippine­s’ (NGCP) 230 kV transmissi­on line.

The company said the technical feasibilit­y of connecting the power plant to NGCP’s Kauswagan 230-kV substation was confirmed in the system impact study ( SIS) that the system operator approved in April 2014.

Aside from the SIS, a facility study has been conducted to determine the technical specificat­ions, the design and operationa­l

criteria, and the cost of the equipment, engineerin­g, procuremen­t and constructi­on, as well as the time required for the proposed connection.

GNPK is a subsidiary of AC Energy in partnershi­p with the Philippine Investment Alliance for Infrastruc­ture Fund and Power Partners. The constructi­on of the plant is in full swing and is expected to be in commercial operation by 2018, AC Energy said in its website.

The facility will operate as a baseload plant to support the power demand and economic developmen­t of Mindanao, it added.

In its initial order, the ERC said it had found the applicatio­n “sufficient in substance” and had set the expository presentati­on, pre- trial conference and presentati­on of evidence on Sept. 7, 2018.

If completed, the plant will be among the biggest power generator in Mindanao, which has an installed capacity of 2,730.1 MW, of which 2,378.8 MW are considered dependable. The southern island’s biggest power facility at present is the Agus hydroelect­ric plants, which has seven units, the biggest of which generates 255 MW.

Newspapers in English

Newspapers from Philippines