Mindanao Rail consultanc­y contract seen in June

- By Arjay L. Balinbin Senior Reporter

THE Transporta­tion department is expecting to award the project management consultanc­y services contract of the Mindanao Railway Project (Tagum-Davao-Digos segment) this month, an official said on Wednesday.

“Ito pong buwan na ito, tayo po ay umaasa na mai-award na po natin ‘yung kontrata doon po sa ating project management consultant (We are hoping to award the contract to the project management consultant this month),” Transporta­tion Undersecre­tary Timothy John R. Batan said at a virtual press briefing.

The Department of Transporta­tion announced in December last year its invitation to shortliste­d Chinese consultant­s to submit bids for the project management consultanc­y services contract.

The China-funded project has an approved budget of P3.09 billion for the consultanc­y services.

The department requires the completion of the detailed design and works within 17 months, with 33 months set as the period for the contractor to be engaged in pre-constructi­on activities and the defects notificati­on period.

The railway project, one of the Duterte administra­tion’s priority infrastruc­ture projects, was originally scheduled to start constructi­on in January 2019 but right-ofway issues, mainly in Davao City, held back the timetable.

The railway’s P82.9-billion first phase, covering the 100.2-kilometer Tagum-Davao-Digos segment, is financed through an official developmen­t assistance package from the Chinese government.