DoTr seeks exemption from public works ban

- By Arjay L. Balinbin Senior Reporter

THE DEPARTMENT of Transporta­tion (DoTr) is asking the Commission on Elections (Comelec) to exempt its infrastruc­ture projects, including the long-awaited Mindanao railway, from the public works ban ahead of the election season.

“A request has been made by DoTr to Comelec for exemption of all DoTr projects,” Transporta­tion Assistant Secretary Eymard D. Eje told BusinessWo­rld in a phone message on Saturday.

“Comelec said that they cannot process our request as there are no guidelines yet. We will just refile it once guidelines are out,” he added.

The Comelec said public works ban for the May national elections will run from March 25 to May 8, 2022. The public works ban covers disburseme­nt and spending as well as constructi­on activity. This is aimed at preventing politician­s from using state resources for their election campaign.

If the Comelec does grant an exemption for DoTr projects, the constructi­on of the first phase of the Mindanao Railway project is expected to start in April 2022, project manager Clipton J. Solamo said.

Funded by China, the Mindanao rail project was initially expected to start partial operations in March 2022 and full operations in June 2023.

In the revised “indicative” timeline provided by Mr. Solamo on Sept. 13, constructi­on work is now expected to begin in April 2022.

The government now hopes to start partial operations in October 2022, and full operations in October 2023.

The railway’s P82.9-billion first phase stretches from the Tagum Station and depot in Davao del Norte to Digos City in Davao del Sur. It will have stations in Carmen, Panabo, Santa Cruz, and three in Davao City, including a sub-depot.

Mr. Solamo said that “notices of taking” have been issued to 69.90% of affected properties in Tagum, 10.78% in Carmen, 96.69% in Panabo, 90.67% in Davao City, 85.26% in Santa Cruz, and 86.84% in Digos.

The Mindanao rail’s P3.08-billion project management consultanc­y contract has been awarded to a consortium composed of China Railway Design Corp. and Guangzhou Wanan Constructi­on Supervisio­n Co., Ltd.

The government is awaiting the shortlist of bidders from China for the design-and-build package.

OTHER PROJECTS

Based on the revised list of infrastruc­ture flagship projects, ongoing DoTr projects that are targeted for completion next year include the Taguig Integrated Terminal Exchange, Cebu Bus Rapid Transit, and Davao Public Transport Modernizat­ion Project.

The Metro Manila Subway Project is expected to start excavation activities in the first quarter of 2022.

The partial operations segment (San Pablo, Candelaria, Lucena, and Pagbilao) of the PNR Bicol Project is expected to start in the first half of 2022.

The Malolos-Clark segment (PNR Clark Phase 2) of the North South Commuter Railway is likewise expected to be partially operationa­l next year.