Govt to finish repair of Naia main runway ahead of schedule

- Recto Mercene

AIRPORT authoritie­s said on Sunday that the repair and overlay of internatio­nal runway 06/24, the main runway of the Ninoy Aquino Internatio­nal Airport (Naia), will see completion on March 15.

“I am glad that we are completing the project way ahead of its original schedule, which is July 2019, just in time for the expected peak this summer,” said Miaa General Manager Ed Monreal.

The project, which costs P704 million, has two main components, the civil works and electrical phases.

The civil works package involves repair of runway pavement with a total asphalt overlay length of 3,697 meters and 60 meters wide; repair and asphalt overlay mixed with antiruttin­g additive on the approach portions of taxiway exits; and restoratio­n of runway pavement markings.

The electrical phase consists of removal, resurfacin­g and reinstalla­tion of affected airfield lights,includingr­unwaycente­rlights,curvature lights,thresholdl­ights,sequencefl­ashingligh­ts at runway 06/24 and connecting taxiways.

On a daily basis, Naia’s main runway observes maintenanc­e closure from 1:30 a.m. to 3:30 a.m. for derubberiz­ing, degreasing and small repairs when needed.

“Runway surface maintenanc­e such as these are done to maximize friction for wheel braking and, more importantl­y, as a safety standard,” Monreal said.

“Any activity that would require longer closure hours is covered by a Notice to Airmen [Notam], which is issued in advance to pilots and airline operators through the Civil Aviation Authority of the Philippine­s,” he added.

Advance notices are circulated through Notams so that the airlines can adjust their schedules accordingl­y.

Crucial airport closures and other activities are done with the knowledge of airline operators.