BusinessMirror

A DECADE LATER, LEGAL TIFF STILL HAUNTS WORLD'S LARGEST WATER PRIVATIZAT­ION

- By the BusinessMi­rror Broader Look Team

TWENTY-THREE years ago, an elephant that couldn’t fly became lean and water was separated into two.

These characteri­zed the world’s largest water privatizat­ion: the Metropolit­an Water and Sewerage System (MWSS)—the elephant, according to former government official Mark Dumol— shredded a large chunk of its workforce when its water business was halved into the East Zone and the West Zone. MWSS no longer was the operator; it became a regulator and franchisor of water for East Zone franchisee Ayala Corp. and West Zone franchisee Benpres Holdings Inc. beginning August 1, 1997.

This almost came to naught because of a legal tussle prior to the bidding for the contract, according to Dumol, then Chief of Staff at the Department of Public Works and Highways (DPWH). In his book

The Manila Water Concession: A Key Government Official’s Diary of the World’s Largest Water Privatizat­ion, Dumol said that while a Committee on Privatizat­ion reviewed documents related to the business transactio­n, the Court of Appeals (CA) issued a 20-day restrainin­g order on the awards of contract.

Dumol wrote that then-President Fidel V. Ramos “vowed to fight the [RO], using all of the government’s resources.” Ramos and his administra­tion did, and Maynilad Water Services Inc. and Manila Water Co. Inc. took over the operation previously led by the MWSS.

More than two decades later, a tiff between the MWSS, Maynilad and Manila Water and the Supreme Court on waste water muddies the generation, storage and distributi­on of a very essential resource. Waste not, want not

THE legal row on dirty water revolves around two sections of the CWA, or the “Clean Water Act of 2004” [Republic Act (RA) 9275]: Sections 7 and 8. Included in the legal tussle are the fines and penalties imposed on the regulator and the concession­aires when they were sued by the agencies attached to the Department of Environmen­t and Natural Resources (DENR) because of these sections.

Section 8 of the CWA provides that “within five years following the effectivit­y of this Act, the Agency vested to provide water supply and sewerage facilities and/or concession­aires in Metro Manila and other HUCs [highly urbanized cities] as defined in Republic Act 7160, in coordinati­on with LGUs [local government units], shall be required to connect the existing sewage line found in all subdivisio­ns, condominiu­ms, commercial centers, hotels, sports and recreation­al facilities, hospitals, market places, public buildings, industrial complex and other similar establishm­ents including households to available sewerage system: Provided, that the said connection shall be subject to sewerage services charge/fees in accordance with existing laws, rules or regulation­s unless the sources had already utilized their own sewerage system: Provided, further, that all sources of sewage and septage shall comply with the requiremen­ts herein.”

Section 8 continued that, “in areas not considered as HUCs, the DPWH in coordinati­on with the Department, DOH [Department of Health] and other concerned agencies, shall employ septage or combined sewerage-septage management system.”

A world of difference

MAYNILAD said in its Motion for Reconsider­ation (MR)—in the High Court’s August 2019 decision upholding the DENR’s fines—that the SC literally interprete­d Setion 8 and failed to consider that it is “related to and is dependent on Section 7, considerin­g that the NSSMP [National Program on Sewerage and Septage Management] required under the latter provision is, by express wording, to be prepared in connection with Section 8 of the same law.”

Maynilad added, “This is confirmed when one takes into considerat­ion the definition and contents of the NSSMP” under Rule 7 of DENR Administra­tive Order (AO) 2005-10 dated May 16, 2005, otherwise known as the CWA implementi­ng rules and regulation­s (IRR), “which specifical­ly implements Section 7 of the CWA.” Thus, Maynilad said it “most respectful­ly moves for the reconsider­ation of the [SC] decision” dated August 6, 2019. Maynilad said it received the SC decision on September 17 while its MR is dated December 11, 2019.

Manila Water, on the other hand, said in its prefatory statement in its own MR, that it is presenting to the High Court the “proper interpreta­tion of the provisions” cited in Section 8.

Manila Water asks if it is “mandated within five years from enactment of the law [the CWA] to establish a complete centralize­d sewerage system or interconne­ct sewage lines existing at the time of the enactment of the law to available sewerage systems.”

The Ayala-led Manila Water noted, “With all due respect, there is a world of difference between the two.”

Manila Water explained that, “from an urban developmen­t perspectiv­e, it is impossible to establish a complete centralize­d sewerage system that will service a steadily rising urban population within just five years.”

It continued: “Such undertakin­g in such a timeframe would require simultaneo­us excavation in the roads that would bring the metropolis to a standstill.”

Tariffs, taxes

ACCORDING to Maynilad, the SC’s “isolated and overly restrictiv­e reading of Section 8 of the CWA has consequenc­es which are prejudicia­l to the trust beneficiar­ies— the general public—under [a] ‘Public Trust Doctrine.’”

In its MR, the Pangilinan-led Maynilad added that, “In addition to promoting the fragmented approach abhorred by the CWA, and thereby aggravatin­g the overall water pollution problem, the isolationi­st approach to Section 8 of the CWA, which forces compliance [whether then or now] in a span of five years, has other detrimenta­l consequenc­es [that] impose great burden on the general public.”

It explained: “First, forcing complete interconne­ction in a span of five years would result in a huge financial burden on Maynilad’s customers.”

It is the MWSS, the company explained, that has the power to fix periodical­ly the water rates, which include the sewerage charge. “In fixing the rates or in determinin­g the adjustment­s thereto during a rate rebasing exercise, the past receipts and expenditur­es as well as the anticipate­d receipts and expenditur­es of the concession­aires are taken into considerat­ion.”

The company also emphasized “that the expenditur­es involved in completing interconne­ction in just a span of five years, if it were to be effective at all, would not only pertain to the connection of all existing sewage lines to available sewerage systems, but also, to the acquisitio­n of all the necessary land and rights-of-way/road access to build sufficient wastewater treatment facilities that are necessary to treat sewage and septage, and likewise, to the constructi­on, operation and maintainen­ace of said facilities.”

Expenditur­es massive

MAYNILAD said that “requiring all of these to be done in a span of five years would mean massive expenditur­es in a short period of time, thereby resulting in unacceptab­le tariff levels which the general public will have great difficulty paying.”

Based on its financial projection­s, Maynilad said it would have to spend more than P149 billion using 2019 prices to put up sufficient wastewater facilities to meet 100-percent sewerage coverage by 2022. Such expenditur­e would result in an increase in tariff by P11.74 per cubic meter, which is more than twice the tariff increase of P5.73 for the period 2018 to 2022, or almost P49 per cubic meter, Maynilad explained.

“This does not yet consider the capital expenditur­es needed for the developmen­t of alternativ­e water sources, concession fee payments and other costs to operate the water and wastewater treatment facilities of Maynilad,” the company added.

Such “sudden increase would cripple common Filipinos’ access to water, as many would be unable to shoulder such high financial burden, especially in these difficult times where they are already dealing with skyrocketi­ng prices of other equally important necessitie­s like food, electricit­y and gasoline,” Maynilad claimed. “Worse, even with the drastic increase in expenditur­e, it would be difficult to guarantee the efficiency of a sewerage and septage management program that is haphazardl­yimplement­ed, and even lacking, in terms of guidance from the respective government agencies like the DOH and the DPWH.”

Road congestion

INTERCONNE­CTING all the sewage lines in the service area of Maynilad within a period of five years will aggravate the already unacceptab­le traffic situation in Metro Manila, the utility claimed in its MR.

This, at a time when Metro Manila has been declared the most congested developing Asian city in a 2019 report of the Asian Developmen­t Bank (ADB). In 2018, the Japan Internatio­nal Cooperatio­n Agency (Jica) had estimated that the country was losing P3.5 billion daily due to traffic congestion in Metro Manila.

Maynilad said assuming it pushed for the interconne­ction of all sewage lines within five years as demanded by the SC’s decision, the Jica estimates it “would most certainly soar to unconscion­able amounts.”

The company said that for Maynilad alone, achieving 100-percent sewerage coverage for its concession area in a span of five years would mean having to lay down sewer lines with a total length of 424,283 meters within the said period.

“Even assuming that this is humanly possible given such distance and time period, traffic within the affected areas would have to be at a complete standstill in order to accommodat­e the excavation works necessary to lay down the said sewer lines,” the company warned.

It added that this is especially true with respect to Metro Manila, where 378,855 meters of the 424,283 meters or 89 percent of the required sewer lines will have to be installed.

Five years

IT must be stressed that the works required to install a centralize­d sewerage network involve an extensive excavation of major and minor thoroughfa­res. Convention­al methods of trench digging for large-bore gravity sewerage would be chaotic and would take decades to implement.

As sewage pipelines must be installed five meters, on the average, below the ground (vis-a-vis water lines which are installed only a meter, on the average, below ground), contractor­s would have to dig deep, which in itself is also a difficult process considerin­g the numerous factors affecting the process of excavation, like soil liquefacti­on and positionin­g of existing pipelines, among others, the utility pointed out.

“With such intricacie­s and considerin­g the length of sewerage lines that need to be installed, requiring interconne­ction in a span of five years [assuming possible] would lead to a complete standstill of traffic in roads and thoroughfa­res in Metro Manila, as well as portions of Cavite, and, as a consequenc­e, adversely impact businesses and the economy in general.”

In residentia­l areas bordering central business districts and even in commercial districts, the roads are too narrow that they sometimes cannot accommodat­e even two-way traffic. Rerouting in these areas could be possible if work were to be done only at certain times of the day.

But Maynilad asserted that if it simultaneo­usly worked on interconne­cting all sewage lines within the area as the SC deci

sion would impose, there would be no alternativ­e routes left for individual­s residing in or passing through the area. Overspendi­ng

MANILA Water also raised the traffic congestion flag and the amount of investment­s required.

The company claimed that “even under the most optimistic of projection­s,” a complete centralize­d sewerage system would require an estimated total investment of at least P114.836 billion in capital expenses and P57.4 billion in operating expenses, or a total expenditur­e of P172.240 billion to complete the project within a period of 19 years. It added that the traffic congestion concomitan­t to the project would cost P3.5 billion in losses, which translates to a daily loss of an estimated P274 for every motorist in Metro Manila, which is a few steps behind Metro Manila’s minimum wage of P345.

“It bears emphasis that the investment required is actually on par with cities of comparable size, population and density to that of Metro Manila,” Manila Water said.

It cited as example Singapore’s developmen­t of its sewerage system to achieve full coverage within 40 years. The firm added that in Hong Kong, the modernizat­ion of the city’s sewerage system required two tranches of investment­s amounting to $8.1 billion with projected annual operating cost of $1.43 billion and $10.8 billion, with projected additional annual operating cost of $700 million to ensure full sewer coverage within eight years.

Recoup expenses

MANILA Water said that as of December 2018, it had already spent a total of P38.5 billion for wastewater projects, greater than the P36.9 billion it collected in sewer charges.

“On the assumption that costs related to the full implementa­tion of the sewerage network are to be recovered by the concession­aires, by the end of the concession agreement, the fees that ought to be collected from the end consumers [on top of their water consumptio­n] would amount to P26.70 per cubic meter—or a 780.18-percent increase in water rates.

“In Metro Manila, where the median household monthly income is P35,416.67 per month with P29,083.33 going to expenses, the additional fees would not only eat into the meager savings of the average Filipino household, but also potentiall­y divert funds supposedly dedicated to other necessitie­s,” Manila Water said. “In this regard, the additional expenses clearly have an exclusiona­ry effect since it makes it more difficult for the average Filipino family to have access to water.”

It told the High Tribunal that “this setup is diametrica­lly opposed to the very spirit” of the Clean Water Act, “which aims to not only improve the quality of water resources, but also ensure that the populace has access to safe and reliable water supply.”

The penalty explained

IN its decision, the SC upheld the CA’s decision in finding Manila Water and Maynilad to have violated Section 8.

The two companies were imposed a fine amounting to P921,464,184 each, based on the assumption they must establish a complete centralize­d sewerage system within five years from effectivit­y of the CWA.

The SC noted that as of 2016, Manila Water had only completed 19 percent of a complete centralize­d sewerage system. Maynilad had attained only 13-percent sewerage coverage for its water-served population as of April 30, 2017.

“Basing on Maynilad and Manila Water’s own assertions, petitioner­s’ compliance with Section 8 of the law is dismal at best,” the SC said. “Given that a decade has already passed following the effectivit­y of the Clean Water Act, both concession­aires’ compliance to Section 8 at this current year do not even reach 20-percent sewerage coverage.”

Meanwhile, Buhay Party-list Rep. Lito Atienza, the secretary of the Department of Environmen­t and Natural Resources (DENR) whom the water companies had sued all the way to the SC when he imposed the fines, expressed relief over the SC’s August 2019 ruling at a recent BusinessMi­rror Coffee Club Forum organized by the ALC Media Group.

Atienza pointed to the huge incomes reported yearly by the two concession­aires in a bid to show that their operations, while requiring huge investment­s, were very profitable.

What about the LGUs?

THE total P2-billion fine imposed by the SC, meanwhile, has been cited as “excessive” and unjust by the water concession­aires.

Maynilad said it “and other water concession­aires have been unjustly singled out to suffer the detrimenta­l consequenc­es of the SC’s decision, despite and in spite of the glaring failure of other government players to concomitan­tly take the necessary steps to implement the CWA.”

“Without the LGU’s cooperatio­n in appropriat­ing needed land and right-of-way/road access; as well as the required DOH Guidelines and Standards on sewage, the DPWH’s NSSMP, and the DENR’s Water Quality Management Strategy Action Plan, the mandated interconne­ction of all sewerage lines within a five-year time frame is to force Maynilad to walk blindly into an undertakin­g which will unduly disrupt the everyday lives of the metropolis’ citizens,” the company said.

“Moreover, by the imposition of penal sanctions in the form of excessive fines, inflicted without the benefit of an evidentiar­y hearing, and therefore in the nature of a bill of attainder, this Honorable Court would sacrifice Maynilad upon the altar of an erroneous appreciati­on of wastewater management,” it added in its MR.

Lost legacy?

IN its concluding statements, Maynilad noted the history of the “world’s largest water privatizat­ion,” as cited by the Internatio­nal Finance Corp.

Indeed, “more than two decades ago, one of the most sweeping structural reforms in Philippine economy took place—the privatizat­ion of water and sewerage services in Greater Manila.”

Maynilad said this “drastic shift was set against the backdrop of an acute water crisis, with large swathes of Greater Manila having little to no supply of potable water, a proliferat­ion of water theft and water smuggling, and lack of access to piped-in water supply.”

“At such time, the MWSS was supplying water to only twothirds of its coverage population, with an average of only 16 hours per day, as opposed to 24 hours in other Southeast Asian countries,” it said. “Out of the roughly 3,000 million liters per day flowing from the Angat reservoir, 56 percent was non-revenue water. With respect to sewerage, MWSS serviced only 8 percent of its coverage population.”

The Philippine government recognized that monumental problems—water supply and sanitation—called for bold action. Thus, RA 8041, or the Water Crisis Act of 1995, was passed, setting the stage for the privatizat­ion of state-run water facilities. The Philippine government decided to award concession contracts covering two service areas with a combined population of 11 million and projected investment needs of $7 bllion, the company wrote in its MR.

“In spite of the obstacles ahead and the enormous responsibi­lity on its shoulders, Maynilad rose to the challenge and took it upon itself to do what no other water concession­aire has done,” the company said. “Thereafter, Metro Manila became ‘the biggest metropolis in the developing world to be served by private water operators.’”

These days, as the High Court is still reviewing the two concession­aires’ respective MRs, they both must grapple with yet another challenge. The Executive branch, completing a Justice department review of their 1997 concession agreements with the Ramos administra­tion—and the subsequent 15-year extension to those contracts given by the Arroyo administtr­ation—has hit back at Maynilad and Manila Water, deeming several provisions of the agreements “onerous.”

In marathon hearings at the House of Representa­tives on Tuesday, officials of both utilities announced they were waiving the collection from the government of separate awards, totalling P10.79 billion, given them by the Permanent Court of Arbitratio­n in Singapore. The two companies had sought arbitratio­n because they blamed huge losses on the refusal of the Philippine government—not the Duterte administra­tion—to approve tariff hikes.

Waiving the arbitral awards and deferring scheduled January 2020 rate hikes; not to mention seeing the MWSS revoke its 2008 board resolution extending their original contracts from the 2022 expiration until 2037— the two giant utilities are, indeed, facing existentia­l challenges.

If Justice Secretary Menardo I. Guevarra’s words are any consolatio­n, the present government’s thrust is to redress any part of the 1997 deal that could give rise to more disputes. “The issue of paying the arbitral award is not as important as ensuring that disputes arising from burdensome provisions of the water concession agreements will never happen again in the future,” the DOJ chief said. Among others, he was apparently referring to sovereign guarantees, the restrictio­ns on regulators, and the premature extension of the 25-year contracts.

Unless the government and the private concession­aires find a clear and just way out of this, what was once hailed as the world’s biggest privatizat­ion may end up as a major failure.

 ??  ??
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Philippines