MGDC secures approval of PRA for Solar City Manila developmen­t

- Roderick L. Abad

MANILA Bay will soon become the location of a commercial, residentia­l and tourism hub in the country after its proponent received the go signal to start the developmen­t of the ambitious project.

The Philippine Reclamatio­n Authority (PRA) has issued a Notice To Mobilize (NTM), as well as a Notice to Commence Actual Reclamatio­n Works (NTCARW), paving the way for the 148-hectare Manila Bay reclamatio­n project of the Manila Goldcoast Developmen­t Corp. (MGDC) to develop the proposed Solar City Manila.

Through its Governing Board Resolution No. 5265 series of 2021, the PRA issued both notices last February 22 to the consortium of the MGDC and the City of Manila.

In the resolution, the PRA said it issued the NTM and the NTCARW pursuant to the issuance of a clearance by no less than the Office of the President (OP), via executive Secretary Salvador Medialdea, to the Manila Bay reclamatio­n project.

Last February 18, it received a memorandum from Medialdea, wherein he gave assurance that the OP does not oppose the start of the project.

“This refers to your Memorandum dated 07 December 2020, requesting authority from the Office of the President to issue the Notice to Mobilize (NTM) and the Notice to Commence Actual Reclamatio­n Works (NTCARW) for the Manila Solar City Project, as well as the confirmati­on of the PRA Board Resolution relative thereto,” the executive secretary said in the memo.

“Pursuant to executive Order Nos. 543 (s. 2006) and 74 (s.2019), considerin­g the Memorandum of this Office dated 01 February 2019 granting clearance to proceed with the Solar City Project, and upon the representa­tions of the PRA on the completion of the documentar­y requiremen­ts and concurrenc­es of the relevant government agencies, please be informed that this Office interposes NO OBJECTION in the grant of the NTM and NTCARW for the Manila Solar City Project, subject to compliance with applicable laws, rules and regulation­s.”

Medialdea said the PRA’S request for NTMS and NTCARWS relative to the Horizon Manila Reclamatio­n Project and Manila Waterfront Reclamatio­n will be acted upon separately.

The MGDC is part of the Solar Group of the Tieng family engaged into entertainm­ent, satellite communicat­ions, and property landbankin­g and developmen­t.

The Solar City Manila project had been proposed more than 30 years ago as the Manila Goldcoast Reclamatio­n Project, which secured in 1991 a greenlight from the then- Public estates Authority, predecesso­r of the PRA, to pursue the project as the Manila-cavite Coastal Road Reclamatio­n-north Sector Reclamatio­n Project (MCCRR-NORTH Sector Reclamatio­n).

Some environmen­tal groups opposed this initiative. even the previous administra­tions of the local government of Manila imposed a ban on reclamatio­n in the city, making the project stalled for years.

On March 31, 2011, the PRA Board affirmed the “previous award of the MCCRR-NORTH Sector Reclamatio­n Project to Manila Goldcoast Developmen­t Corp.”