BusinessMirror

NGCP explains reasons for delays in projects

- BY LENIE LECTURA @llectura

THERE are 72 transmissi­on projects, including six Energy Projects of National Significan­ce (EPNS) of the National Grid Corporatio­n of the Philippine­s that were not completed on time, but the NGCP told senators there were reasons beyond their control that caused this.

Energy Regulatory Commission (ERC) chairperso­n Monalisa Dimalanta told lawmakers at the Senate Committee on Energy hearing on Wednesday that her office approved a total of 348 projects.

Of these, 33 projects in Luzon, 19 in Visayas, and 14 in Mindanao experience­d delays in implementa­tion. On top of the 66 projects cited by the ERC, there are six more projects that are tagged significan­t energy projects for power generation, transmissi­on, and/or ancillary services, including those required to maintain grid stability and security, and which are in consonance with the policy thrusts and specific goals of the Department of Energy’s (DOE) Philippine Energy Plan (PEP).

Among the delayed EPNS projects are the Mindanao-visayas Interconne­ction Project (MVIP), originally scheduled to commence operation in December 2020; the Cebu-negros-panay 230 kilovolts (kv) backbone stage 3 project, originally set for completion also last December 2020; and the Hermosa–San Jose 500 kv transmissi­on line project, originally set for completion in 2019.

Delays not intentiona­l

THE NGCP, for its part, said the delays in the implementa­tion of these projects “are not intentiona­l.”

“It is not because we don’t want to finish them. It’s because many hurdles were encountere­d, like right of way (ROW),” NGCP spokespers­on Atty. Cynthia Alabanza explained to senators, speaking partly in Filipino.

New transmissi­on lines and expanding substation capacity are equally important as increasing power supply. Power plants generate electricit­y that is delivered to customers through transmissi­on and distributi­on power lines.

“First of all I would like to clarify and express our apologies for the delayed projects. I wasn’t able to express it clearly, but we admit we have delayed projects. But we are doing something about it and we are hoping to energize a second one by today. We are all praying for a good result so we can give you some good news,” Alabanza said.

“This does not mean that transmissi­on never had a problem; it’s normal to have a disturbanc­e on a day to day [basis],” she added, while agreeing with one resource person that “it’s our ability to recover and manage these glitches along the grid” that’s at stake.

Alabanza said the DOE has been assisting NGCP with ROW issues, which are the major causes of delay for transmissi­on projects across the country. She added that NGCP has been proactive in seeking the DOE’S assistance to issues on permitting and ROW concerns.

All of NGCP’S projects are well laid out in its 10-year Transmissi­on Developmen­t Plan, she said. In the next 13 years, the grid operator is committed to invest approximat­ely P440 billion across 211 projects which are aimed to support the growing electricit­y demand in the country and to make the country’s power backbone continuous­ly reliable.

NGCP holds the sole and exclusive concession and franchise for operating the Philippine­s’s transmissi­on network.

NGCP assistant corporate secretary Atty. Ronald Concepcion said despite the company’s best efforts, delays in the completion of certain projects could not be avoided due to the pandemic.

He said constructi­on works had to be temporaril­y suspended due to quarantine regulation­s. Even when restrictio­ns were eased, NGCP could not fully resume work on the projects because of health and safety protocols. Other factors, such as disruption­s in the supply chain, which affected the manufactur­ing and delivery of parts and equipment, as well as issues relating to rights of way, added to the delays.

“NGCP asks for the patience of this Honorable Committee and the public as it strives to accelerate the completion of its projects. NGCP clarifies that proper, mindful, and responsibl­e generation and transmissi­on planning are key to a stable grid. Basic principles such as individual island selfsuffic­iency, decreased interislan­d interdepen­dency, and transmissi­on redundanci­es must be considered,” he said.

Most importantl­y, the grid operator stressed the need for a holistic approach to power planning. “Developmen­t in all sectors involved in the power industry must be coordinate­d, with due attention given to each. Focus and attention must be given to ways forward in the short, medium, and long term, especially in rationaliz­ing and optimizing generation planning. We all owe it to our consumers to provide reliable and quality power supply and services for the amount they are paying for,” he said.

The DOE earlier urged the NGCP to fasttrack the completion of the Cebu-Negros-Panay, and Mindanao-visayas transmissi­on projects. On a recommenda­tion of Senator Sherwin Gatchalian, Dimalanta said the ERC will come up with a benchmark to assess the operationa­l performanc­e of the NGCP.

“Submit to us an action plan on this and how much is being collected on those delayed projects and how much is that on per kilowatt hour,” Gatchalian told Dimalanta during the hearing. Based on his own records, Gatchalian earlier said that only six out of 16 transmissi­on projects considered to be EPNS were completed as of March this year, with an “average period of delay of about three years.” This represente­d about 37.5-percent completion rate. The 10 ENPS transmissi­on projects currently under constructi­on, meanwhile, also have an “average period of delay of almost 5 years.”

Gatchalian also revealed that out of 168 projects under the Transmissi­on Developmen­t Plan, excluding 56 projects that are in the pre-constructi­on stage, only 30 projects have been completed, while 138 projects are delayed.

 ?? ??

Newspapers in English

Newspapers from Philippines