LRMC schedules LRT 1 station improvements
In preparation for the delivery of new trains, Light Rail Manila Corporation (LRMC) disclosed yesterday that all 20 passenger stations of the existing LRT Line 1 system will be improved to enhance accessibility, safety and security of commuters.
“When government brings in new light-rail vehicles (LRVs), we expect passenger traffic to increase; thus, the need to make sure that the stations are ready to handle the expanded capacity,” according to LRMC President and CEO Jesus P. Francisco.
The plan is consistent with the company's commitment to provide better service and give commuters the best station environment.
The Station Improvement Project will start with Doroteo Jose Station, the interchange terminal of LRT Lines 1 and 2 in Sta. Cruz, Manila. After the improvements, it is expected that stations will be well-lit and organized to allow better passenger flow.
Construction for Doroteo Jose Station is targeted to start on December 2015.
In March 2016, the two biggest stations, Central and Baclaran, and three smaller stations, R. Papa, Abad Santos, and Gil Puyat will follow. The rest of the 14 will start in May and August 2016.
“The Station Improvement Project complements our plan to enhance passenger safety, comfort and convenience and is aligned with our objective of improving the efficiency of the LRT 1 system,” he added.
LRT Line 1 currently accommodates a daily average of 400,000 commuters from Baclaran in Pasay City to Roosevelt in Quezon City.
LRMC took over operation and maintenance of LRT Line 1 last September 12. It will also be responsible for the construction of the 11.7-kilometer extension from the present end point at Baclaran to the Niog area in Bacoor, Cavite.
The extended rail line is expected to help increase the capacity of LRT 1 from 500,000 to 800,000 passengers daily and benefit more than four million residents in the southern part of Metro Manila and of Cavite.