Salceda confident Duterte admin can complete Bicol Int’l Airport

- By NIÑO N. LUCES

LEGAZPI CITY - Albay 2nd District Representa­tive Joey Salceda on Thursday said he is confident that the Duterte administra­tion could revive and complete the stalled Bicol

Internatio­nal Airport project and further lift Bicol tourism. Since the project broke ground in 2005, it is only 52.50 percent complete as of November 30, 2018.

Salceda said that only the constructi­on of the runway, taxiway apron and perimeter fence and airstrips have been completed.

The detailed engineerin­g and constructi­on supervisio­n is only 52.50 percent complete, while the constructi­on of landslide facilities (site developmen­t and other buildings) - Pack 2A is 47 percent complete.

The Passenger Terminal Building is only eight percent complete.

“Nakakahiya na naunahan pa ng Panglao na nagsimula nung 2012 samantalan­g nagsimula ang Bicol Internatio­nal Airport nung 2005 pa. It truly reflects that we have lost our national capacity to execute big-ticket projects since Marcos era and there is reasonable optimism that the executive decisivene­ss of the Duterte administra­tion could restore that and deliver the Bicol Internatio­nal Airport vital to the main potential of Bicol - tourism”, Salceda said.

During the meeting of the Committee on Transporta­tion, Briefing and Update on Bicol Internatio­nal Airport last Wednesday, Salceda said that the Department of Transporta­tion (DOTR) is looking at the airport’s opening in 2020.

Salceda said he is confident that the R4.798-billion project will be completed before the end of President Duterte’s term.