Manila Bulletin

SMC builds temporary steel ramp to ease SLEX traffic

- By EMMIE V. ABADILLA

To ease traffic congestion on the South Luzon Expressway (SLEX) while building the Skyway Extension, San Miguel Corporatio­n (SMC) has started installing a temporary steel onramp connecting the Alabang viaduct to the Skyway.

The ramp will have two lanes and will be operationa­l by December 1, 2019, expanding the northbound section of SLEX in Alabang from three to five.

“The limitation­s in the original design of the SLEX is that it has five lanes coming from Susana Heights heading to Alabang," SMC President and Chief Operating Officer Ramon S. Ang explained.

"However, this narrows to four lanes at the Alabang viaduct and connects with the Skyway at-grade that has only three lanes. This is the main reason why Alabang has always been a chokepoint for traffic,” he added.

Hence, he said that “this is the main reason why we are building the Skyway extension.”

"We want to make the northbound and southbound sections five lanes each all throughout,” Ang further said.

Less than two months ago, Skyway’s Operation and Maintenanc­e (O&M) closed one northbound at-grade lane of the Skyway in the Alabang area to start preliminar­y work on the project. The stretch of slow-moving vehicles on that day reached 19 kilometers, way above the daily average of 10 kilometers.

“My commitment to you is that by December 1, all preliminar­y work will be done. We will reopen the closed-off lane and restore use of all three at-grade northbound lanes. Traffic will not only return to “normal” levels, it will improve because we are also opening the temporary ramp from the Alabang viaduct going up to Skyway. With a total of five lanes northbound, we can expect a significan­t improvemen­t in the traffic,” Ang said.

The Skyway Extension project is a more than ₱10-billion undertakin­g funded by San Miguel to extend the Skyway all the way to the Susana Heights/ Muntinlupa-Cavite Expressway (MCX).

Newspapers in English

Newspapers from Philippines