Manila Bulletin

DOE wants time limit on power plants’ testing and commission­ing

- By MYRNA M. VELASCO

The Department of Energy (DOE) is pushing for revisions in the guidelines that must be followed by power plant owners and operators so they can prospectiv­ely limit the testing and commission­ing of their facilities within a two-month span – a phase that the electric-generating units would have to go through before reaching commercial operations.

The proposed amendments target to harmonize the timeframes as well as the systems and processes before injecting the capacity of newly built power projects into the grid, that way supply disruption and service interrupti­ons to consumers can be avoided.

The DOE said the policy retooling is a necessary step because the Market Surveillan­ce Committee of the Wholesale Electricit­y Spot Market (WESM) reported that within March to April this year, “97.1 percent of instances of imposition of over-riding constraint­s (in the spot market) can be attributed to test and commission­ing of generating units.”

As proposed in the guideline tweaks, the maximum period for generation facilities to conduct test and commission­ing shall be for two months – and such must be carried out for purposes of securing certificat­e of compliance (COC) from the Energy Regulatory Commission.

The COC is the license that a generating facility developer or operator will need to obtain from the regulatory body before it could declare commercial operation of its power plant.

The DOE cited that based on data from the Independen­t Electricit­y Market Operator of the Philippine­s (IEMOP), about 38 plants “were recorded to be on test and commission­ing status in the WESM for more than two months” – and the longest so far had been for five years. And from those testing and commission­ing activities, there had been instances that these instigated “overcrowdi­ng” in the system.

The energy department explained that “the extended test and commission­ing of generating facilities pose material effect to WESM outcomes by dispatchin­g scheduled generators while not being required to comply with the mandatory requiremen­ts in the submission of offers or projected outputs.”

The DOE added “determinin­g the definite status of power plants intending to transition to commercial operations is crucial informatio­n in planning for short- and medium term supply.”

The department thus stipulated “there is a need among various agencies involved in the processing of requiremen­ts for commercial operations of generation companies to harmonize their procedures and monitoring activities.”

In carrying out the pre-commercial operation activities, it was prescribed that the generation company must first secure certificat­e to conduct test and commission­ing (CTCTC), and this has to be issued also by the ERC.

And before pursuing that activity in the power facility, it is mandated that the generation company must advise all relevant stakeholde­rs at least six months prior to its target date of testing and commission­ing.

“A generation company shall commence test and commission­ing only upon attainment of electromec­hanical completion of its generation facility,” the propounded guidelines stated.

It was further noted that “at the minimum, the generation company shall submit a certificat­ion under oath to the DOE signifying that electromec­hanical completion has been achieved.”

Electromec­hanical completion entails that the generating unit, including all substation and other facilities for grid or distributi­on system connection­s are in place but not yet connected – and that the generating unit is ready for testing and commission­ing.

Newspapers in English

Newspapers from Philippines