Dumuloc earth-fill dam ready by 2025

-

DAGUPAN CITY, Pangasinan: The National Irrigation Administra­tion office in aims to complete the constructi­on of the Dumuloc earth-fill dam in Bugallon, Pangasinan in 2025.

NIA Ilocos Regional Manager Gaudencio de Vera said the department first repaired the old dam in Dumuloc and is continuing the repair of Laguit Dam and the constructi­on of canal lining in preparatio­n for the constructi­on of the overall structure of the 40-meter Dumuloc earth-fill dam.

“The project aims to provide a quality irrigation system to Bugallon farmers to increase their production,” de Vera said.

With an estimated project cost of P1.651 billion, about 1,484 farmers and their families are expected to benefit from the improvemen­t of irrigation and water distributi­on.

He said: “Over 1,632 hectares of land can be irrigated during the wet season while 1,300 hectares for the dry season.”

“The project will cover the villages of Umanday, Laguit Centro, Poblacion, San Francisco, Hacienda, Cayanga, Portic, Salomague Norte, Salomague Sur, Bacabac and Bolaoen,” he added.

Early this month, NIA Acting Administra­tor Eddie Guillen inspected the

Dumuloc earth-fill dam together with Deputy Administra­tor for Administra­tive and Finance Sector Ralph Lauren Du and de Vera.

Guillen also visited Gov. Ramon Guico 3rd to discuss the irrigation developmen­t plans in the province.

Moreover, he had the chance to talk to the seven irrigation associatio­n presidents of Bugallon town and laid down the different projects for them.

Once the constructi­on of the Dumuloc dam is completed, Guillen aims to convert it into an agritouris­m enterprise.

Meanwhile, the local government unit of Bugallon expressed its support for the dam’s constructi­on.

Municipal Administra­tor Amado Aquino said that although the large structure is not yet finished, the initial constructi­ons made by NIA are of big help because the farms that were not irrigated before have been reached and are able to plant crops in the summer season.

According to NIA’s data, the physical accomplish­ment of the project is 28.49 percent. The groundbrea­king of the Dumuloc earth-fill dam was conducted in November 2021.