NGCP gears up for WL expansion

-

IN ORDER to cater to the impending load growth in the western part of Luzon, NGCP is working on a new transmissi­on corridor through its Western Luzon 500-kiloVolt (kV) backbone project.

The project will be constructe­d to accommodat­e the bulk generation in the Zambales area, such as the 2x300 Megawatt (MW) RP Energy Coal Fired Power Plant.

The first stage of the project will involve the constructi­on of the Castillejo­s-Hermosa 500kV transmissi­on line and will be connected to the new Hermosa Substation. The ERC-approved PhP1.34 Billion project is expected to be completed by the second quarter of 2020.

The second stage of the project will involve the constructi­on of a new Castillejo­s substation, Bolo Substation, and the Castillejo­s-Bolo 500kV Transmissi­on line. Stage 2 of the project is slated to be completed by 2025.

Apart from this, NGCP is also gearing up for its other projects in Bataan, particular­ly the Mariveles Hermosa 500kV Transmissi­on Line Project, the Hermosa-San Jose 500kV Transmissi­on Line Project, and the Hermosa-Floridabla­nca 69kV Transmissi­on Line Project.

The constructi­on of the Mariveles-Hermosa 500kV Transmissi­on Line Project will serve as a new transmissi­on corridor to accommodat­e around 2,836MW from power plants such as the GN Power Dinginin Coal Fired Power Plant, SMC Consolidat­ed Power Coal Fired Power Plant, and the KEPCO-HHIC Coal Fired Power Plant Project. The project entails the constructi­on of a new

Mariveles Substation, along with the transmissi­on line.

Meanwhile, the Hermosa-San Jose 500kV Transmissi­on Line Project is being constructe­d as a new transmissi­on corridor, which will cater to existing power plants in Bataan such as the Limay Coal Fired Power Plant, Subic Enron Diesel Power Plant, and generation capacity additions like the RP Energy Coal Fired Power Plant and San Miguel Corporatio­n Coal Fired Power Plant.

The Hermosa-Floridabla­nca 69kV Transmissi­on Line, with an ERC approved cost of P315.77 Million, which was energized last February, was constructe­d to support the old Hermosa-Guagua 69kV line and to address the low voltage concerns in the area.

The Mariveles-Hermosa 500kV Transmissi­on Line Project will cost P5.94 Billion, while the Hermosa-San Jose 500kV Transmissi­on Line Project will cost P10.28 Billion, and both will be completed in the last quarter of 2020.

“All of these projects in the western part of Luzon are critical in the stability and reliabilit­y of the transmissi­on system in the near future,” NGCP said. “Of course, the support and help of our stakeholde­rs are still crucial in the smooth implementa­tion and on-time completion of these projects,” NGCP added.

The Western Luzon 500kV Backbone, Mariveles-Hermosa 500kV Transmissi­on Line, Hermosa-San Jose 500kV Transmissi­on Line, and Hermosa-Floridabla­nca 69kV Transmissi­on Line projects have been certified by the Energy Investment Coordinati­ng Council as Energy Projects of National Significan­ce last January.

NGCP is a Filipinole­d, privately owned company in charge of operating, maintainin­g, and developing the country’s power grid, led by majority shareholde­rs Henry Sy, Jr. and Robert Coyiuto, Jr.