DCWD finishes pipeline improvemen­t projects

-

THE DAVAO City Water District has completed two pipeline improvemen­t projects for Dumoy Water Supply System (WSS) on Aug. 15, 2019.

These were the pipelaying of 400mm diameter steel pipe transmissi­on line along Bago Gallera Road to Davao-Cotabato Highway and pipeline improvemen­t along Talomo Road from junction Puan along Talomo Road to DavaoCotab­ato Road.

It can be recalled that the constructi­on of the said projects necessitat­ed water service interrupti­ons which took place on June 15 to 16, 2019 and July 24 and 26, 2019 affecting areas served by Line 2 of Dumoy WSS and on July 10 to 11, 2019 affecting areas served by Line 1 of the same WSS for the tapping works of its pipelines.

With the commission­ing of these two transmissi­on lines, friction loss from Dumoy field wells to Talomo Pumping Station has been reduced thus, increasing the input volume of water supplied to the pumping station. In turn, this increased availabili­ty of water supply and pressure for the service coverage areas of Dumoy WSS.

Based on DCWD’s post-evaluation, water supply has improved in areas near DILG Matina, Governor Generoso Bridge, Jacinto Street corner Quezon Boulevard, and Gempisaw corner Sta. Ana Avenue.

These areas used to experience intermitte­nt

water supply especially during peak hours of water use. The completion of the projects also improved the water supply and pressure in areas served by Line 1 of Dumoy WSS because of the 9,000 cubic meters per day added volume to the Dumoy system.

Dumoy is DCWD’s largest water supply system that serves approximat­ely 71,000 service connection­s under Line 1 and 60,000 service connection­s under Line 2.

DCWD thanks its customers for their cooperatio­n and understand­ing.

DCWD also assures its customers of continuous implementa­tion of water service improvemen­t to provide 24/7 water supply with adequate pressure.